work on reconstruction of entrance group in the TC "Auchan-Tambov"
1.1. Preparing Street zone — reconstruction of the existing pit. The pit area is 2.5 x 3 meters. Depth is 10 cm. Drainage systems and preheating is not necessary. 1.2. Preparation of entrance Group (Tambour TC). The area is 160 m2, each door doorway width 2.1 m: • Removing floor coverings (tiles). Device input group for pit installation Coir mats. Installed in the pit in the input group matting should coincide with the Street level zone. 1.3. Delivery Of Materials: • For outdoor zone is Grjazezaderzhivajushhee device (steel grating with a support structure to 45/190RS). • For the input panel — matting (aluminium with inserts: bristles, rubber, textiles, scratcher). The load on materials shopping trolleys, customers SHOPPING CENTER, cleaning scrubber driers. 1.4. Installation Materials. Collapse
| Archived | \"IMMOShAN\" OOO | 13.09.2017 12:00 |