Request for Proposals No. 1399504 
Provision of services for the dismantling of the old gates, fabrication and installation of new industrial lifting and sectional doors on the subject of "STU"

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
25.99.99.218  Услуги по изготовлению памятников, ограждений, ворот из металла по индивидуальному заказу населения
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:06.12.2019 18:00
Last edited:03.12.2019 10:15
Organizer (Initiator):"Vezerford" OOO
Additional info
Per-item bid submission
Bidders can submit their proposals for certain lots of the call for bids, but necessarily for all the items within a selected lot
:
Not applicable. Proposal shall cover all the items of the selected lots
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing per unit price for each item from their previously submitted proposal.
:
10 000 RUB
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Prices, confirmed the commercial part of the offer remain unchanged for the entire contract period and include all costs and expenses of the Contractor related to the acquisition of materials and their delivery, execution of works and so forth. Obligatory payments, in accordance with Russian legislation,
Payment deferred payment upon completion, within 90 calendar days, but not earlier than 60 calendar days.
Delivery terms:General performance requirements:
The work must be performed by a contractor for in full accordance with the agreed time schedule of works and estimates approved as part of the contract.
The contractor should have a license (SRO) needed to perform the work on the project of the Customer;
Before starting work, and the signing of the contract, the Contractor shall submit a final version of the budget documentation, agree on a schedule of works.
Materials, components, tools and equipment used at work, are included in the cost of the work and are not subject to additional payment by the Customer.
Perform necessary trained and certified to perform the corresponding operations specialists. Every employee of a contractor must have a certificate confirming the qualifications and the necessary approvals for specialized types of work.
All the materials used to carry out repair work must comply with state standards and other regulatory documents (material quality evaluation according to the quality certificate, the certificate of conformity and passports). Contractor shall be responsible for the compliance of the materials used to state standards and technical conditions.
All works are carried out without disrupting the schedule of work and production processes of the customer company. Place of storage of materials and waste must be agreed with the customer prior to the start of work. Upon completion of garbage should be taken out and disposed of by and at the expense of the Contractor.
Production work is carried out during working hours of the Customer Enterprise. Weekend work and working time is possible in exceptional cases and agreed separately with the customer in advance.
After completion of the work the Contractor shall provide the Customer with the executive and accounting documentation duly executed in accordance with the requirements of Russian legislation. (The act of acceptance of work performed, the invoice and so on.).

The purpose of works:
Replacing the door in industrial building in order to save thermal energy, providing comfort and a favorable temperature conditions.

Requirements to quality of works:
Quality of work must meet the requirements of the applicable rules and regulations, national standards, technical documentation and other regulations.
Acceptance of work by a commission of the Customer with the participation of the authorized representatives of the Contractor.
The work carried out in compliance with MOE requirements and so on. The supervisory authorities, should be handed over the selection committee of the corresponding supervisory body.
The warranty period for work performed for at least 36 months. The warranty period The contractor must provide travel specialists and elimination of defects during 2 days (working days) after receipt of the request from the customer.

The security requirements of work:
The entire staff of a contractor should be instructed in safety and fire safety, familiarization with the procedures and policies of the company "Weatherford" to safely perform the work.
When carrying out the Contractor shall comply with the environmental protection requirements of the current legislation of the RF environment, guided by the applicable building codes, fire safety rules and safe operation of construction machines and mechanisms, environmental and sanitary-hygienic and other standards, internal regulations (standards and policies OT HSE) of the Customer.
The Contractor shall be solely responsible for the safe conduct of work, compliance with fire safety regulations, safety regulations at work, accident investigation, if they do occur.
Leaders and professionals must be trained and certified in the field of industrial safety and labor protection.

Terms of carrying out all the works: December 2019 January 2020.

The type and amount of work: Dismantling and disposal of old gates, fabrication and installation of new industrial lifting and sectional doors.
Georeferencing:461040, Russia, Orenburg region, Buzuluk, Magistralnaya str., 12.
Comments:
Comments:
1. Please, submit any questions concerning the bidding procedure via e-marketplace functionality ("Request for Clarifications").
2. By their proposals electronically to participants of this procedure is necessary before the opening of the envelopes to attach all the necessary documents simultaneously with the proposal, signed by the authorized person and stamped by the participating organization of the procedure. In case a participant fails to comply with this requirement bidding organizer has the right not to consider such participant's proposal.
Proposals validity period - 30 days at least.

Note: Note, this RFP is not a notice of tender (public tender) or a public offer and is not subject to Articles 447 - 449, Part I, and Articles 1057 - 1061, Part II, of the Civil Code of the Russian Federation. Thus, this procedure does not impose the corresponding amount of civil obligations on the Customer, and the Customer reserves the right to refuse all the received proposals for any reason, or to terminate the selection procedure at any time, without incurring any liability before the participants.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:Алексей Мазунин +79619079393
Aleksey.Mazunin@.weatherford.com

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Задать вопрос
Latest submitted bids
Status of bidding: archived.
Total bids: 4. More >>