Request for Proposals No. 3471506 
Selection of a contractor for the SMR on the object: "Gasoline processing complex LLC "Slavyansk ECO" (3,4 stage of construction). Inter-shop technological overpass C (tit.247-30) (3rd stage of construction)". Driving control piles. Static...

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
Quantity:1 усл.ед.
Total price:Price not specified
Currency:RUB
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:08.11.2023 16:00
Плановая дата подведения итогов
Организатор указал предполагаемую дату подведения итогов. Если в процедуре не будут подведены итоги при наступлении этой даты, то участники могут запросить их самостоятельно
:
30.11.2023
Last edited:08.11.2023 13:38
Bidding cancellation date:21.11.2023 13:59
Organizer (Initiator):«Slavyansk EСО» LLC
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Hide prices and bidders' names during bids submission period:Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Payment terms:Payment for the amount of work actually performed - no later than 60 calendar days
Delivery terms:According to clause 4 of the Terms of Reference
Georeferencing:353560, Russia, Krasnodar Territory, Slavyansky district, Mayevskoye settlement, kh. Mayevsky, Northern Territory, s/u 1; 23:27:1402000:499
Comments:
Construction and installation work must be carried out in accordance with the Requirements Specification in full.

Supply of materials and equipment: The offer must contain the cost of materials and equipment necessary to perform the QMS, taking into account delivery to the facility.

The estimated documentation is developed on the basis of the procedure for determining the price of works. (Appendix No. 1), the requirements of the above Procedure are MANDATORY for use.

Term of work:
1. Registration and delivery of IR D - 15 calendar days from the date of conclusion of the Contract;
2. Preparatory work, including staff mobilization, organization and arrangement of the construction site – 10 days from the date of conclusion of the Contract;
3. Execution of a full range of construction and installation works in accordance with the PPR and the test program, the schedule agreed by the parties and the deadline in the Technical and Commercial Proposal.

REQUIREMENTS for Bidders.

Requirements for Bidders of the procurement procedure are specified in clause 10 of the Terms of Reference:
1. Availability of a certificate of registration in the SRO with admission to perform construction and installation work on especially hazardous capital construction facilities;
2. Resource reference (availability and list of machinery, equipment and human resources);
3. Availability of qualified, certified personnel and having the appropriate confirmations - protocols (IT and workers), including electrical engineering with the 5th electrical safety group and persons responsible for the safe production of work. lifting mechanisms.
4. Registration of admission of personnel, transport, materials, equipment and tools in accordance with the Requirements (Appendix).

Scanned copies of the necessary documents are attached to the Technical and Commercial Proposal (extract of the SRO, with admission to especially hazardous facilities; resource certificate; confirmation of the availability of personnel with the necessary qualifications).

REQUIREMENTS for the development of estimate documentation.

The estimated documentation is developed on the basis of the Procedure for determining the price of works (Appendix). The requirements of the above Procedure are MANDATORY for use.

To calculate the materials (materials to rate), funds for the production of works according to the Requirements Specification.

WE PAY YOUR Please NOTE:!!
The cost of the main materials in the estimates is indicated for reference and is used to correctly determine the limited costs, the cost of the main MTR is not taken into account when choosing the Winner (the winner is determined by the cost of work).
After determining the Winner by the cost of the SMR, the Winner coordinates the cost of the main materials with the Customer's MTO service in the RVP format at the time of conclusion of the contract.

REQUIREMENTS for the technical and commercial proposal (sample Technical and Commercial Proposal in the attachment).

The Technical and Commercial Proposal must necessarily contain the following information:
1. Terms of payment (advance payment is possible under BG).
2. Terms of work.
3. The warranty period for the work performed.

Appendices to the Technical and Commercial Proposal:
1. Local estimates in two formats (Excel, Grand ESTIMATE not lower than version 10, in the database of the Krasnodar Territory (2014 edition)
2. A separate statement of delivery, according to the standard RVP.
3. Agreement with the terms, type and form of the contract for the implementation of the SMR (form in the attachment)
4. Extract from the SRO registry;
5. Reference list;
6. Resource reference (availability and list of equipment, equipment and human resources).
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.

Organizer has decided to cancel the call for bids.
Call for bids cancellation date: 21.11.2023 at 13:59.
call for bids cancellation reason:

В связи с выходом изменений в проект

Total bids: Hidden