1. JSC "Stoylensky GOK". The quarry. An increase in the extraction and transportation of non-oxidized ferruginous quartzites to 36.8 million tons per year with the possibility of increasing to 46.8 million tons per year. II stage of construction....
1. JSC "Stoylensky GOK". The quarry. An increase in the extraction and transportation of non-oxidized ferruginous quartzites to 36.8 million tons per year with the possibility of increasing to 46.8 million tons per year. II stage of construction. DSP. Combined traction substation No. 5 110/10kV and 110/6kV(GPP-05) Inv. No. 1057800;
2. JSC "Stoylensky GOK". The quarry. An increase in the extraction and transportation of non-oxidized ferruginous quartzites to 36.8 million tons per year with the possibility of increasing to 46.8 million tons per year. II stage of construction". CSP. Combined traction substation No. 6 (GPP-06)".
SPP 22-0800-26, 22-0800-27 Electrical installation worksCollapse
Организатор указал предполагаемую дату подведения итогов. Если в процедуре не будут подведены итоги при наступлении этой даты, то участники могут запросить их самостоятельно
Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension with settings
If within the last 10 minutes before bid submission deadline the best offer changes, bid submission deadline in the call for bids will be automatically extended by 10 minutes from the time when the latest bid was submitted.
:
10 minutes
Payment terms:
the payment of the actually completed works is made monthly within 30 calendar days from the date of signing the forms KS-2, KS-3 (SMR, NDP) and acts of completed works (Design and Survey Works).
Delivery terms:
The cost of the set of works in the tender offer (Appendix No. 2) is determined at the current price level, based on our own experience and existing needs for organizing and performing the amount of work, the cost of setting up temporary buildings and structures, winter price increases, the cost of work on PPR, delivery of all goods, including from the Customer's warehouses, mobilization, business trips the costs, protection of the facility and all other costs that may arise during the execution of the work include all costs of the Contractor and are fixed for the entire period of the work.
The value of the contractual coefficient is defined as the ratio of the fixed contract price of the SMR, taking into account the materials provided by the Contractor, to the estimated cost of the SMR, taking into account the materials provided by the Contractor, in the estimated standards of the NLMK PJSC drill after the release of the working and estimated documentation.
The cost of commissioning "idle" is taken into account in the tender offer at current prices separately.
Georeferencing:
Belgorod region, Stary Oskol, South industrial zone p/r, pl-contractual Counterparty Fabrichnaya pr-d-4, d. 1
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.