Request for Proposals No. 2628648 
Corrosion protection of inter-shop gas pipelines through the territory of EPM-NEZ JSC in 2021.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Corrosion protection of inter-shop gas pipelines through the territory of EPM-NEZ JSC in 2021.
See terms of reference (Complex service)

OKPD2 category:
43.29  Работы строительно-монтажные прочие
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:16.04.2021 17:41 (was extended by 41 min, 57 sec)
Last edited:05.04.2021 16:38
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:In the terms of reference
Delivery terms:1. Application of JSC "EPM-NEZ", Novocherkassk

2. Purpose of manufacturing
2.1. Corrosion protection of gas pipelines

3. List and scope of work performed
3.1. List of works
No. P / P Inventory of work and defects Unit. rev. amount
1. Gas pipeline from the southern side of the central heating center building No. 2 to the entrance to the room 4 of the central heating furnace building No. 2 Ø108, L-220m., Elevation + 6m. m2 74.7
2. Gas pipeline from the lowering to the inlet valve Ø100 in the section of the EVP LLC "DKG" Ø108, L-165m., Elevation + 6m. m2 56
3. Gas pipeline along the wall of the calcining unit of the special-purpose center, building No. 2 Ø108, L-80m., Elevation + 6m. m2 27
4. Gas pipeline along the wall of the calcining unit of the special-purpose center, building No. 2 Ø89, L-80m., Elevation + 6m. m2 22.3
5. Gas pipeline on the western wall of TsPOiP Ø89, L-100m., Elevation + 7m. m2 28
6. Gas pipeline from the western side of the ground-based PSK SPC building No. 1 Ø325, L-80m., Elevation + 6m. m2 81
7. Gas pipeline from the western side of the ground-based PSK SPC building No. 1 Ø273, L-80m., Elevation + 6m. m2 68
8. Gas pipeline from the western side of the ground-based PSK SPC building No. 1 Ø159, L-80m., Elevation + 6m. m2 40

3.2 Scope of work performed:
No. P / P Inventory of work and defects Unit of measurement Quantity
1. Sandblasting of gas pipelines 100m2 of the painted surface 3.97
1. Dedusting of gas pipelines 100m2 of the painted surface 3.97
2. Degreasing of gas pipelines 100m2 of the painted surface 3.97
3. Painting of gas pipelines with a primer in 2 layers 100m2 of the surface to be painted 3.97
4. Painting of gas pipelines with PF-115 enamel in 2 layers 100m2 of the painted surface 3.97

5. Turnaround time
Start of work 04.2021.
Completion of work 06.2021.

6. Materials, mechanisms, equipment and tools provided by the Contractor.
6.1. The works are performed from the material of the performer.
6.2. Lifting mechanisms (car lifter) are provided by the contractor.
6.3. The tool for performing the work is provided by the contractor.

7. Requirements for the performer
7.1. The contractor must have the necessary production and human resources to carry out this work, be a member of a self-regulatory organization (SRO).
7.2. To clarify the conditions for the performance of work, familiarization with the object, the arrival of the Contractor's representatives to the Customer is mandatory.
7.3. Certification of the head, engineering technician and executors for industrial safety and labor protection at HIF. According to Appendix No. 1.
7.4. Provision of health and safety measures for safe work methods at the facility.

8. Conditions of work
8.1. Work at an operating enterprise.
8.2. Development of PPR or PPRK is carried out by the Contractor.
8.3. Lifting mechanisms for receiving, transporting and supplying materials are provided by the Contractor.
8.4. The warranty period for corrosion protection of gas pipelines is 24 months.

9. Terms of payment
9.1. Upon manufacture.
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
The participant who took part in the procedure (made an offer), before the deadline for accepting applications, must upload the following documents to the system:
1. Charter (with all additions and changes, if any).
2. Certificate of state registration.
3. Tax registration certificate.
4. Extract from the Unified State Register of Legal Entities.
5. Balance sheet as of the last reporting date with the tax authority's mark of acceptance.
6. Documents confirming the authority of the representative to sign documents:
- Decision (Protocol).
- Power of attorney.
7. Work proposal (see the file "Work proposal")
8. Contact persons: Chief Power Engineer - Fateev Vitaly Valerievich,
Tel. 8 (8635) 29-44-83 VFateev@energoprom.ru
Leading power engineer - Vorotyntsev Alexander Nikolaevich,
Tel. 8 (8635) 29-43-94 AVorotyncev@energoprom.ru
Senior equipment repair technician - Alexander Yurievich Kononov,
Tel. 8 (8635) 29-47-34 AKononov@energoprom.ru
9. Certificate of compliance with the requirements of ISO 9001: 2008 (if available)
This request is not a notice of a tender or auction and does not give any rights to participants, does not entail the emergence of any obligations other than those expressly indicated in the notice.
10. Requirements for the performer:
- Permits (SRO, licenses, permits).
- Development by the contractor of PPR, PPRK, RTI.
- Availability of attestation of the head, engineering technician, industrial safety workers at the HIF.
- Availability of medical clearance of personnel to work at HIF.
—Before issuing a work permit for work, the Contractor is obliged to provide the Customer with the following documents: copies of documents confirming the availability of a labor protection service and / or a labor protection specialist in the contractor (order for appointment to a position in the contractor, certificate of a labor protection specialist) or the existence of an agreement with an accredited organization in the field of labor protection services.
To consider the application, it is MANDATORY to provide a commercial proposal.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 14.05.2021 at 15:35
and selected the winner: "AL'IaNS" OOO – (Bidder 6) (Лепендин А.Н.) submitting a bid dated of 16.04.2021 16:39 totalling to 1 150 000,00 RUB (price excl. of VAT)
Notifications have been sent to bidders.
Total bids: 6. More >>