Request for Proposals No. 1465600 
Engineering support and preparation of drilling fluids

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Engineering support and preparation of drilling fluids

OKPD2 category:
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:13.03.2020 15:05
Bids opening date:13.03.2020 15:05
Last edited:06.03.2020 11:34
Organizer (Initiator):"UK "TATBURNEFT'" OOO
Additional info
Per-item bid submission
Bidders can submit a bid for separate items within the call for bids
:
Applicable
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Payment for services is made within 90 calendar days from the moment of signing of certificates of acceptance of rendered services and provision of invoice.
Delivery terms:By location of the customer's facilities of Severo-Izmaylovskoye field
Georeferencing:423450, Russia, Republic of Tatarstan (Tatarstan), Almetyevsk, Musa Jalil str., 51
Comments:
This price request procedure is not a competition procedure. The Organizer has the right to refuse all offers received for any reason or to terminate the procedure for requesting prices at any time without incurring any liability to the Suppliers!
1. BOILD CATEGORY - Inclined directional.
2. NUMBER OF WELLS - 3.
3. WELL DESIGN: Direction Ø= 426х9,5mm -20 m;
Conductor Ø= 324х8,9mm — 150 m;
Technical column Ø= 245х8,9mm —750m;
Ex.column Ø= 168х8,9mm —2100m;
5. Drilling mud:
Interval, m Solution Type Parameters (API)
0-150 Clay Ud.weight - 1,11 g/cm3; HV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 cP; DNS - 70-120 dPa; SNC - 24-72/48-96 dPa; Tv phase content - up to 10%; Lubrication content - not less than 1%.
150-750 Biopolymer Fresh Drill Solution (BDP). Ud.weight - 1.14 g/cm3; HV - 55-70s; F - 2-3 cm3/30min; pH - 9-11; PV - 12-25 cP; DNS - 80-120 dPa; SNC - 24-48/28-62 dPa; Tv phase content - up to 20%; Cl-not more than 1000 mg/l; Adhesion - not more than 5 deg; Lubrication content - not less than 3%.
1872-2100 Biopolymer Freshwater Drilling Solution (BDP). Ud.weight - 1.14 g/cm3; HV - 55-70s; F - 2-3 cm3/30min; pH - 9-11; PV - 12-25 cP; DNS - 80-120 dPa; SNC - 24-48/28-62 dPa; Tv phase content - up to 20%; Cl-not more than 1000 mg/l; Adhesion - not more than 5 deg; Lubrication content - not less than 3%.
6. Duration of drilling of one well - 35 days.
7. TERRITORIAL LOCATION - Severo-Izmaylovskoye deposit
8. ACCEPTANCE OF THE CONTRACT IN THE EDITORIAL OFFICE OF THE CUSTOMER.
9. THE WORK MUST BE CARRIED OUT IN - HOUSE WITHOUT THE INVOLVEMENT OF SUBCONTRACTORS.$
10. Equipment, materials and equipment for the provision of services must have all the necessary valid certificates of quality and, if necessary, permits for use, transport and storage.
11. The import/export of chemical reagents, equipment and process engineer shall be carried out by the Contractor.
12. Provision of personal transport, wagon-houses for accommodation of personnel at the object of work, communication, Internet is carried out by Contractor, preparation unit for drilling mud.
13. The scope of the Services for this project includes the provision of personnel, chemical reagents, equipment, software products for the organization of works, preparation of work programs, plans, events, logistics diagrams, engineering support, analysis of the work done, reports, including recommendations to the Customer, etc. Replacement of materials and equipment, as well as the use of additional materials is allowed only in agreement with the Customer.
14. The cost of 1 cubic meter of drilling mud includes the costs of preparation with the help of a mobile unit of preparation of drilling mud, processing to maintain the specified parameters of the drilling mud (excluding geological complications), engineering and technological support, delivery of specialists, preparation of drilling mud, materials, equipment, wagon-houses to the object of performance of works. It is necessary to have a mobile preparation unit at the entire stage of construction of wells and a crane manipulator for preparation of drilling mud.
15. It is obligatory to use in the composition of drilling mud not less than 2 organic inhibitors (polyglycols, polyamines, etc.) for stabilization of clay rocks with a concentration of not less than 30 kg/m3 total.
16. Submission of a commercial offer according to the established form (Appendix to the specification)
17. Save at least 50% of biopolymer fresh drilling mud from the drilling interval under the technical column, for drilling the production column.
18. Payment for services is made within 90 calendar days from the moment of signing of certificates of acceptance of rendered services and provision of invoice

Submission of a commercial offer according to the established form (Appendix to the specification)
For questions of this lot please contact: Askarov Rail Falihovich — Chief Specialist in Solution Service Management Service 8 (8553) 389-315, 8-987-424-43-44
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Total bids: 5. More >>