Request for Proposals No. 2447724 
Engineering support and preparation of drilling fluids

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:15.09.2020 16:00
Bids opening date:16.09.2020 16:00
Last edited:10.09.2020 11:39
Organizer (Initiator):"UK "TATBURNEFT'" OOO
Additional info
Per-item bid submission
Bidders can submit a bid for separate items within the call for bids
:
Applicable
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Payment for services is made within 120 calendar days from the moment of signing of the certificates of delivery and acceptance of the services rendered and the provision of an invoice.
Delivery terms:At the location of the customer's objects. TERRITORAL LOCATION - Orenburg region, 200km from the city. Orenburg, Alexandrovskoye deposit.
Georeferencing:423450, Russia, Republic of Tatarstan (Tatarstan), Almetyevsk, Musa Jalil str., 51
Comments:
This price request procedure is not a competition procedure. The Organizer has the right to refuse all offers received for any reason or terminate the procedure of asking prices at any time without incurring any liability to the Supplier!

1. Well CATEGORY - 1 obliquely directional well; 1 horizontal
2. NUMBER OF WELLS - 2.

2.1. Well construction №1: Direction Ø426 - 50 m;
Conductor Ø324mm - (50-500m);
Intermediate column Ø245mm - (500-1077) m;
Operating column Ø168.3 mm - (1077-2655).
Interval, m Solution Type Parameters
0-230 GR Ud.Weight - 1.12 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
230-500 GR Ud.Weight - 1.26 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
500-1077 GR Ud.Weight - 1.26 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
1077-2655 IGBR Ud.Weight - 1.18 g/cm3; UV - 55-70s; F - 2-3 cm3/30min; pH - 9-11; PV - 12-25 SP; CSN - 80-120 dPa; SNA - 24-48/28-62 dPa; Tv.phase content - up to 20%; Lipidity - not more than 6 degrees; Contents lubricants - not less than 2%.
Drilling time of the well - 46 days.
2.2. Well construction №2: Direction Ø426 - 50 m;
Conductor Ø324mm - (50-500m);
Intermediate column Ø245mm - (500-1077) m;
Pilot barrel Ø168.3 mm - (1077-2407).
cut from pilot barrel 1894-1906 Operating column Ø168.3 mm - (1906-2381).
Secret column Ø114 mm - (2381-2681).
Interval, m Solution Type Parameters
0-230 GR Ud.Weight - 1.12 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
230-500 GR Ud.Weight - 1.26 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
500-1077 GR Ud.Weight - 1.26 g/cm3; UV - 35-50s; F - 6-8 cm3/30min; pH - 8-10; PV - 10-20 SP; CSN - 70-120 dPa; SNA - 24-72/48-96 dPa; Tv phase content - up to 10%; lubrication content - not less than 1%.
1077-2407/1906-2381 IGBR Ud.Weight - 1.16 g/cm3; UV - 55-70s; F - 2-3 cm3/30min; pH - 9-11; PV - 12-25 SP; CSN - 80-120 dPa; SNA - 24-48/28-62 dPa; Tv - content - up to 20%; mg/l; Stickiness - no more than 6 hail; lubrication content - not less than 2%.
2381-2681 IGBR Ud.Weight - 1.12 g/cm3; UV - 55-70s; F - 2-3 cm3/30min; pH - 9-11; PV - 12-25 SP; CSN - 80-120 dPa; SNA - 24-48/28-62 dPa; Tv - up to 20%; SL- - more than 60 000Lipidity - not more than 6 hail; lubrication content - not less than 3%.
Drilling duration of one well - 68 days.
3. TERRITORAL LOCATION - Orenburg region, 200km from the city. Orenburg, Aleksandrovskoye deposit.
4. ACCEPTANCE OF THE CONTRACT IN THE ORDER OF THE CUSTOMER.
5. WORK MUST BE DONE IN - HOUSE WITHOUT THE INVOLVEMENT OF SUBCONTRACTING ORGANIZATIONS.$
6. Equipment, materials and equipment for the provision of services must have all necessary valid certificates of quality and, if necessary, permits for use, transportation and storage.
7. The importance/export of chemical reagents, equipment and a technological engineer is carried out by the Contractor.
8. Providing with private transport, wagons-houses for accommodation of personnel on the object of work, communication, internet is carried out by the Contractor, the preparation unit for brown solution.
9. The scope of Services for this project includes the provision of personnel, chemical reagents, equipment, software products for the organization of works, preparation of work programs, plans, activities, logistics diagrams, engineering support, analytics of work done, reports, including recommendations to the Customer, etc. The replacement of materials and equipment, as well as the use of additional materials, is allowed only in agreement with the Customer.
10. The cost of 1 cubic meter of drilling mud includes the cost of preparation with the help of a mobile unit of drilling mud preparation, processing to maintain the specified parameters of the drilling mud (excluding geological complications), engineering and technological support, delivery of specialists, preparation of drilling mud, materials, equipment, wagonhouses to the object of work. It is necessary to have a mobile preparation unit at the entire stage of the construction of wells and a tap manipulator for the preparation of drilling mud.
11. It is necessary to use in the composition of drilling mud at least 2 organic inhibitors (polyglycoli, polyamines, etc.) for the stabilization of clay rocks with a concentration of not less than 30 kg/m3 in total, as well as it is necessary to have an emergency stock at the well, not less than 1 ton of Glital lubricating additive. To ensure the presence of inert fillers at the facility of providing services. Asphaltenes, hydrocarbon-based lubricant additive, Polyacrylamides, Barite weighter are not allowed.
12. Provision of a commercial offer according to the established form (Schedule Annex)
13. Payment of services is made within 120 calendar days from the moment of signing of the certificates of delivery and acceptance of services rendered and invoice

Provision of a commercial offer according to the established form (Schedule Annex)
For questions of this lot, please contact: Askarov Rail Falihovich — Chief Specialist in Solution Services Management Service 8 (8553) 389-315, 8-987-424-43-44
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:Аскаров Раиль Фалихович – главный специалист по растворному сервису Службы по управлению сервисами 8(8553) 389-315, 8-987-424-43-44

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Total bids: 3. More >>