Request for Proposals No. 834907 
fabrication and installation of ventilation systems from umbrellas graphitization furnaces section no. 8 HRS of material provided by the contractor for the drawings ...

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:02.06.2017 15:00
Last edited:29.05.2017 08:57
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:in fact of fulfilled works
Delivery terms:1. Application of OJSC "EPM-NJeZ", g. Novocherkassk2. The purpose of the execution of works: Reconstruction of ventilation system of graphitization furnace hoods section no. 8 HRS. Removal of waste gases from furnaces HRS section no. 8.

3. Scope of work. disassembly, manufacturing and installation.

1. Annex No. 1 TK features. S 020. 12738 2. Annex No. 2 TK features. ART 12738 KM

4. Requirements to the Executive Director. 4.1. Certification Manager, ENGINEERS and performers in industrial safety and labour protection on GCO. According to the annex No. 1. 4.2 Ensure HSE measures, safe methods of work on the project. 5. Conditions of work the work on existing Enterprise 5.1. 5.2. Work is done from the material executor 5.3. Hoisting machines and mechanisms for loading provides artist. 5.4 electrical welding and gas cutting equipment and oxygen, propane, auxiliary materials provides artist. 5.5. Vehicles for transporting garbage, scrap or other waste provides artist.

6. Place of work: The territory of the customer and the contractor.

7. Turnaround time: June-August, 2017. Metal fabrication in June, July and August installation Contractor gives the customer a guarantee of 12 months on the executed work-. 8. Terms of payment: Payment is required fractionally, after the actual execution of works.

9. General requirements. 9.1. To tender the contractor provides:

-certificate of admission to a specific kind of works that affect safety of capital construction (SRO certificate to perform work described in this Setting).
-

estimates for the manufacturing and Assembly work.
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
Party, participating in the procedure (who offer) before the expiry of the deadline, is required to download to your system the following documents: 1. Bylaws (as amended and supplemented, if they were). 2. Certificate about State registration. 3. Certificate of registration tax accounting. 4. Extract from the UNIFIED STATE REGISTER. 5. Balance sheet as of the last reporting date with tax authority stamp of acceptance. 6. Documents confirming the powers of the representative to sign documents: — Decision (Protocol)-power of attorney. 7. Proposal for execution of works (see file "work Proposal") 8. Contact person: Chesnokov Alexey Leonidovich. Environmental engineer Office of OTPBJeGOiChS, 8 86352-94530 phone, e-mail addresses of responsible persons: AChesnokov@Energoprom.ru DSalihov@Energoprom.ru 9. Certificate of conformity to requirements of standard ISO 9001: 2008 (if available), this request is not a notice about the contest or an auction and does not confer any rights of parties entails no duties except the expressly stated in the notice. 10. Executive requirements:-permits (CPO, licenses, tolerances) — development of PPR, Executive LEAD, RTI. — Availability of certification Manager, ENGINEERS, working on industrial safety at PBO. — medical admission personnel work at the PBO.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 19.06.2017 at 14:32
and declared the call for bids void.
Обоснование: Принято только одно предложение
Notifications have been sent to bidders.
Total bids: 1. More >>