Request for Proposals No. 3215357 
Manufacture and installation of auxiliary metal structures in axes 1-21/A-BE Tula

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Manufacture and installation of auxiliary metal structures in axes 1-21/A-BE Tula

OKPD2 category:
Quantity:1 усл.ед
Total price:Price not specified
Currency:RUB
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:06.02.2023 12:00
Last edited:30.01.2023 13:19
Organizer (Initiator):OOO "VB DEVELOPMENT"
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing the total lot price from their previously submitted proposal.
:
1% of total amount
Auto-extension
If within the last 10 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 10 minutes from the time the last bid is submitted.
:
10 minutes
Payment terms:Mostly post-payment
Delivery terms:The scope and list of works includes, but is not limited to, the composition listed below. The works are carried out by the Contractor in full, "turnkey", by the Contractor's forces, means and mechanisms, including all necessary consumables and related expenses.
1. Manufacture, supply and installation of metal structures (MK), fire escapes, frames for equipment on the roof, structures of porches and canopies, structures for strengthening gates and doors, frames for equipment on the roof, according to the requirements of the Statement of work volumes (Appendix A),
Terms of Reference and Working Documentation (Appendix B).
2. Purchase and delivery of consumables, fasteners and other
materials necessary for work.
3. Mobilization of all necessary equipment and tools
to the work site in the amount necessary for high-quality work in accordance with the GPR.
4. Input control and quality control of materials with an entry in the journal and certificates.
5. Delivery, unloading, warehousing, moving and lifting of materials to
the place of work.
6. Installation of the MK in accordance with the instructions of the Working Documentation and
Technical specifications.
7. Transfer of a set of Executive documentation and delivery of works.
8. other work necessary for the successful completion of the work.
9. Demobilization.
According to the Customer's decision, part or the full volume of materials
listed in the Statement of Work Volumes can be supplied by the Customer as a tolling material. The obligation, in this
case, for entrance control, acceptance, unloading, moving to the place of work, completeness, protection and safety of material and
property, etc., remains with the Contractor.
Requirements for the work
1. Prepare and coordinate with the Customer and the General Designer the section
KMD for all MK. Without an agreed section of the KMD, the production
of metal structures and their installation is prohibited.
2. Before the start of installation, perform a verification geodetic survey and
acceptance of structures for compliance with the planned and high-altitude positions,
notify the Customer and Contractor about excess deviations and discrepancies with the Executive survey
.
3. Before the start of the work, coordinate the PPR and a detailed schedule
of work with the Customer.
4. The mass of the metal in the KMD section should not differ from the mass of the metal
the KM section is more than 5%.
5. It is not allowed to replace profile sections, steel grades, hardware grades, and
other materials without approval from the design organization.
6. To coordinate with the Customer a detailed schedule for the delivery of MK, to determine and
coordinate with the Customer the place of unloading and storage of materials.
7. To clean the metal before painting, use the sandblasting
cleaning method, Sa-2-½ "Very thorough jet cleaning of metal"
8. Metal structures are manufactured and painted at the factory
and come to the facility ready for installation. The total thickness of the AKZ
coating is 80 microns.
9. Before painting metal structures to be coated
with flame retardants, the manufacturer must coordinate
the scheme and type of painting with the fire protection project of metal structures (with
the fire protection contractor) to clarify the structures subject
to structural or paint fire protection.
10. Metal structures to be coated with flame retardants
should be covered with two layers of GF-021 primer. Before painting, the manufacturer must coordinate the painting scheme with the fire protection project
of metal structures to clarify the structures subject
to structural or paint fire protection.
Color of painting of metal structures:
Additional metal door reinforcements, gates - RAL 7035
Frames for equipment - RAL 7035
Porches RAL 7035
Fire stairs RAL 7035
11. Carry out preliminary inspection and assembly before sending
the shipping stamps.
12.All metal structures during unloading pass 100% input
control for compliance with their section KMD, quality and thickness of the AKZ.
13.All bolts, nuts and washers, including high-strength ones, must have a zinc
coating.
14. All assembly units must have indelible markings or tags
with the element number, according to the assembly schemes of KM and KMD.
15.MK must be packed in bags, with gaskets between the elements,
packages must be rigidly tightened, protective
gaskets should be installed under the ties. Transportation should be carried out rigidly fixed in the body,
to avoid damage to the AKZ.
16. Flanges, ends, linings, etc. elements that are not subject to AKZ must be packed in a steak film.
17.Metal structures are stored in accordance with GOST 23118-2019 and SP 70.13330.2012.
18. To install frames for equipment on the roof, including all related work, hardware and consumables - are included in the scope of work of the Contractor.
19. Welding of frames for equipment on the roof, to farms is not allowed.
20.Installation of porches, including installation of piles, concreting, all related works, hardware, anchors and consumables are included in the scope of work of the Contractor.
21. Installation of fire escapes, including all related works, hardware, anchors and consumables - are included in the scope of work of the Contractor.
Additionally, according to the Statement of the scope of work and RD, to make and mount a fire. Ladder Lp2 in axes 46/A-K'.
22. Installation of framing of doorways and gates, including all related works, hardware, anchors and consumables - are included in the scope of work of the Contractor.
23. Each batch of MK must be accompanied by quality certificates for each
product, certificates for materials, the results of the narrow control,
the results of the control of the AKZ coating.
24. All work is carried out "turnkey" with materials and by the Contractor. The
cost of the work includes, temporary lighting, a wheel washing point and its
maintenance and accommodation and meals for personnel, the construction of temporary
roads, networks and structures, sanitary facilities and their maintenance, maintenance and maintenance of the work site and
approaches to it, consumables, overlaps, overlaps and docking
materials, travel expenses, materials and equipment for
laying, maintenance and heating of concrete, personal protective
equipment for safety, snow cleaning, drainage, collection, removal and disposal
of garbage, safety of materials, equipment and property, obtaining and
developing the necessary accompanying documents for the production of works
and other costs necessary for the successful completion of work within the time limits set by the contract and with the quality corresponding to requirements
The Customer, this TOR and the Working Documentation.
25.When building an object, follow the RD-11-02-2006 regarding
the composition and list of acts of inspection of works and survey
structures, a set of Executive documentation.
26. When performing work and after completion of work, it is necessary to
clean the territory and garbage collection.
27. Any changes in the composition and content of the work, the
equipment and materials used are documented in writing
and sent to the Customer for consideration.
28.Payment for the work performed is made for
the amount of work actually performed, on the basis of executive documentation, with confirmation
by technical supervision and a surveyor of the customer. The volumes and cost
of the work performed are closed "in the body", i.e. taking into account the coefficient of compaction,
decompression, spills, losses during transportation and
unloading /loading, overlaps, scraps, overlaps, coefficient for irreparable losses, coefficient of metal deposition, etc. should be
included in the cost of work.
29.The Contractor undertakes to prepare and send to the Customer a daily
report, according to the Customer's form, on the work performed.
Georeferencing:Tula region, Aleksinsky district, Novoe Kleymenovo village
Comments:
Work should be carried out in accordance with the requirements of the standards:
SP 70.13330.2012 Load-bearing and enclosing structures.
GOST 23118-2019 Steel construction structures.
GOST 21779-82 is a system for ensuring the accuracy of geometric parameters in construction. SP 16.13330.2017 Steel structures GOST 21.502-2016 System of design documentation for construction. Rules for the implementation of working documentation of metal structures GOST R 21.101-2020 System of design documentation for construction GOST R 58387-2019 Adhesive anchors for fixing in concrete test methods
SP 20.13330.2016 "Loads and impacts" SP 43.13330.2012 "Structures of industrial enterprises" SP 28.13330.2012 "Protection of building structures from corrosion" SP 53-101-98 "Manufacture and quality control of steel building structures" in force on the territory of the Russian Federation, Working documentation, Statement
of work, Contract and this Technical Specification, other technical and regulatory documents;
The materials, equipment, and tools used must
comply with GOST, technical specifications applicable in the territory of the Russian Federation, and have the necessary certificates and permits.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Total bids: Hidden