Request for Proposals No. 3509813 
Manufacture and supply of basement panels (concrete)Penza

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Manufacture and supply of basement panels (concrete)Penza
Manufacture and supply of prefabricated reinforced concrete structures

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:11.12.2023 12:00
Last edited:04.12.2023 23:41
Organizer (Initiator):OOO "VB DEVELOPMENT"
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing the total lot price from their previously submitted proposal.
:
1% of total amount
Auto-extension
If within the last 10 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 10 minutes from the time the last bid is submitted.
:
10 minutes
Payment terms:post-payment
Delivery terms:6.
Production and delivery time

According to the Schedule of work – Appendix B.
7. Scope of work 1. To manufacture prefabricated w /w base panels according to
Statement of work volumes: Appendix A.
2. Deliver the products to the Customer's facility.
8. Initial
data
provided by
e by the customer
Appendix A: Statement of work volumes
Appendix B: A set of Working documentation QL, QL.
Appendix B: Schedule of work.
9. Requirements for
carrying
out works
1. Requirements for manufacturing, materials – according to Working drawings.
2. Before mass production of prefabricated concrete elements, it is necessary
to produce a reference sample, deliver it to the Customer's facility and draw
up a certificate of acceptance of the standard by the customer.
3. The release strength of the concrete of the finished panels should be at least 70% in
summer and at least 85% in winter. The manufacturer is obliged
to guarantee that concrete reaches its design strength.
4. Cracks are not allowed in concrete, except for shrinkage and
surface technological cracks, the width of which should not exceed
0.1mm.
5. The opening of the surface of the embedded parts must be protected from
corrosion (the recommended protection scheme is to cover with zinc
-containing paint "Cynol" in one layer). The color of the protective coating should be
close to the color of concrete.
6. The open surfaces of embedded products must be cleaned of
inrush.
7. The category of the surface of the panels should not be lower according to GOST 13015-2012
- A2 for the outer and visible inner sides and A4 for the invisible
inner sides. The panel should be made with the outer side facing down
(facing the formwork).
8. Manufacturing accuracy class according to GOST 21779-82:
- linear dimensions - 3;
- flatness - 2;
- pendicularity -3.
9. Storage and transportation of panels should be carried out in accordance with
the requirements of GOST 31310-2015, with the following additions:
- move and install the panels using
self-balancing traverses that ensure the vertical
position of the panels (the slope of the slings to the vertical is allowed no more
15 grad.)
- the support of the panels in the warehouse and during transportation should be carried out only
with an internal bearing layer on special gaskets (wooden,
rubber, etc.) so that the outer layer of the panel from the bottom
always has an air gap to the top of the support of at least 20 mm.
10. Since combustible insulation is used in the panels
, fire safety measures must be provided, no
fire is allowed during manufacturing, storage, transportation and
installation.
11. Each panel must have a quality certificate, certificates of
conformity.
12. Each panel must have an indelible tag with the name and
number of the project.
Georeferencing:440000, Russia, Penza region, Penza
Comments:
10. List
of normative technical
documents, in
accordance with
the requirements
of which
it is necessary
to perform
the work
1. Work should be carried out in accordance with the requirements of the standards:
GOST 26633-85 Concrete is heavy. Technical conditions
GOST 21779-82 System for ensuring the accuracy of geometric parameters in
construction
GOST 13015-2012 Concrete and reinforced concrete products for construction
GOST 14098-2014 Welded fittings and embedded products
of reinforced concrete structures
RD-11-02- 2006 Requirements for the composition and procedure for maintaining executive
documentation
SP 70.13330.2012 Load-bearing and enclosing structures
SP 435.1325800.2018 Concrete and reinforced concrete monolithic structures
GOST R 21.1101-2013 System of project documentation for construction
(SPDS)
operating on the territory of the Russian Federation, Working documentation, Statement
of work volumes, Contract and this Technical Specification, other
technical and regulatory documents;
2. The materials, equipment, tools used must
comply with GOST, technical specifications applicable in the territory of the Russian Federation, have
the necessary certificates and permits.
11. Guarantee of the
result of the work
The guarantee for the result of the work performed by the Contractor is 5 years.
12. Requirements
to labor protection
and
Safety equipment.
The contractor is obliged to strictly comply with the requirements of OT and TB, in
accordance with the requirements of Russian legislation, as well
as internal requirements of the enterprise when carrying out work. The Contractor
is obliged to immediately respond to all comments from the Customer
on violations of the Occupational Health and Safety rules, and immediately eliminate such comments.
The customer has the right to stop the contractor's work until
the violations are eliminated, in case such violations may lead to serious
injuries or death of the contractor's employees. The customer has the right to impose a fine
on the Contractor for not fulfilling the Customer's requirements to eliminate violations
rules of Occupational Health and Safety.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Total bids: Hidden