installation and commissioning Instrumentation schemes when organising a sealed drain raw materials in workshop No. 4. work performed under the project "re-equipment of the hazardous production facility" mercantile "Sealed drain to an existing flyover plum raw materials, basic set of working drawings 054-02-14-AK.
Perform installation work «turnkey»:
1. Execution of works in full accordance with the GJeSN. For example, for mandatory testing of cables cable insulation status before and after laying, marking lived.
2. Execution of the commissioning of turnkey integrated testing. When the contractor must perform:
- preparatory work-organizational and engineering preparation of works, acquaintance with the technical documentation, production technology, basic and auxiliary equipment, development and coordination with customer graphics and programs commissioning works;
- works carried out to individual tests, verification of technical automation, including checking the technical condition of the instruments and apparatus with bringing their parameters to the standards established by the regulations; check the completed installation of technical facilities for compliance with the requirements of the project and the instructions of the manufacturer;
- works carried out between individual tests-autonomous adjustment systems, settings adjustment systems during individual testing of technological equipment;
- commissioning works during the period of comprehensive testing equipment-integrated adjustment of systems;
- testing automated systems together with technological equipment, one instance of concepts of the project changes identified in the process of adjusting works;
- delivery of technical equipment, systems and programmes in operation in ensuring sustainability of technological equipment on the modes and the release of the first batch of products;
- registration and acceptance-delivery documentation.Collapse
Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:
the customer makes payment to the Contractor upon completion of a separate phase not later than 15 (fifteen) banking days after signing acceptance certificate of executed works, information on the cost of work performed and costs and provide invoices. Calculations are made by transferring money to the account of the contractor. By agreement of the parties may be subject to other forms of payment stipulated by the current legislation.
Delivery terms:
contract date-01.03.2018 g.
Completion date-16.04.2018 g.
Georeferencing:
Россия, Омская область, г. Омск, 644049, ул. Барабинская, 20
Comments: 1. The contractor working on the Model Treaty of the customer.
2. requirements to the composition of the tender participant specified in the job.
3. Contact person for all technical questions to:
Chief metrologist Dmitriev, Aleksandr Mikhailovich (3812) 42-34-81.
4. Please note that the request for proposals is not an auction and not subject to the requirements of articles 447-449 of the Civil Code of the Russian Federation.
The organizer has the right to request for proposals, how to choose the winner of the procedure and complete it, rejecting all incoming proposals.
The organizer of the RFP defines the winner of the request for proposals on the basis of criteria. The lowest price offered during the request for proposals does not mean a definitive victory in the procedure.
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.