Request for Proposals No. 860912 
the Organization and carrying out of construction and installation works, at the following address: The Republic of Bashkortostan, Blagoveschensk (beer production plant)

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Quantity:1 шт.
Per unit price:55 000 000,00 RUB (price incl. VAT, VAT: 18%)
Total price:55 000 000,00 RUB (price incl. VAT)
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:25.07.2017 12:44 (was extended by 44 min, 45 sec)
Bids opening date:25.07.2017 15:44
Last edited:18.07.2017 20:00
Organizer (Initiator):\"ASTRA\" OOO
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Bid security is required:Bidding organizer requires the participants to provide bank guarantee
Банковская гарантия:Security amount: 10,00%
Valid from date: 01.09.2017
Guarantee expiration date: 01.08.2018
Guarantee cases: Обязательство не предоставлять заведомо ложные сведения или намеренно искажать информацию или документы, приведенные в составе Предложения Note! You need to inquire of the organizer of the procedure about the bid security form (guarantee, down payment, other variants), in the purchase documentation.
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:according to the draft Treaty. the customer shall pay to the contractor an advance payment for the purchase of materials: in the amount of 10% of the contract price in the 30 days after the conclusion of the contract and the provision of a bank guarantee client to 20 of each month pays for the volume of entrepreneurial works according to signed acts of acceptance of the executed works in form of COP 2 and references about the value of work performed and costs form COP-3. Final calculation is made for the contractual price prescribed in paragraph 3.1. This agreement and specified in supplementary agreements with proportional advance payment paid off, no later than 30 days from the date of signing by the parties of the taking over certificate of executed works
Delivery terms:the contract price includes the cost of construction, Executive, surveying, surveying control object with the subsequent drawing it on tablets topographic plan, technical, technical passport of a cadastral passport, cost of materials, equipment, transport, travel and other expenses, including VAT and all other taxes, duties and other charges, which the contractor should pay in accordance with the terms of the contract or on other grounds.
Georeferencing:Республика Башкортостан, Благовещенск
Comments:
on matters relating to: CMP projects, timing and execution of works, payment: Tel. contact: 8 906-81-73-030 Voronchihin Aleksej Nikolaevich, e-mail: ufa.zavod.pivo@gmail.com
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 29.07.2017 at 09:23
and selected the winner: "SU № 1" OOO – (Bidder 4) (Гуфранов А.А.) submitting a bid dated of 25.07.2017 09:14 totalling to 16 283 660,00 RUB (price incl. VAT)
Обоснование: Существенными условиями заключения Контракта является наименьшая цена договора, предложенная Участниками (с учетом всех включенных расходов, связанных с исполнением Контракта).