Open Request for proposals for the right to conclude a contract for the development of working documents and execution of construction and installation works with the delivery of equipment by title: "Construction of TP 15/0.4 kv, power...
Open Request for proposals for the right to conclude a contract for the development of working documents and execution of construction and installation works with the delivery of equipment by title: "Construction of TP 15/0.4 kv, power transmission line 15 kv from Вl 15-146 (Inv. № 5114680), Power transmission line 0.4 kv in the p. Konstantinovka Gurievsky Go" Development of working documentation and execution of construction and installation works with delivery of equipment by title: "Construction of TP 15/0.4 kv, power transmission line 15 kv from Вl 15-146 (Inv. № 5114680), Power transmission line 0.4 kv in the p. Konstantinovka Gurievsky Go"Collapse
OKPD2 category:
42.22.12.112 Линии электропередачи местные кабельные
OKVED2 category:
42.22.2 Строительство местных линий электропередачи и связи
Not applicable. Proposal shall cover the entire lot.
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing the total lot price from their previously submitted proposal.
:
0,06% of total amount
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:
payment of the completed works of the first stage is carried out on the basis of the act of acceptance of the executed design works and invoice within 30 calendar days from the moment of signing of the mentioned documents. Payment of the executed works of the second stage is carried out on the basis of the certificate of acceptance of executed works (Form № KS-2), the reference on cost of the executed works (Form № KS-3), the act of results of works and the invoice within 30 calendar days from the moment of signing Specified documents
Delivery terms:
period of development of working documentation and execution of construction and installation works with equipment delivery-no more than 6 months. From the moment of signing the contract
Venue of bids examination:
г. Калининград, ул. Театральная, 34
Date and time of bids consideration:
19.11.2018 18:00
Results date and time:
20.11.2018 18:00
Georeferencing:
Россия, Калининградская область,
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:
Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
The Organizer has announced the results on 20.11.2018 at 16:06
and selected the winner: "Iantar'energoservis" OAO – (Bidder 1) (Котенёв С.В.) submitting a bid dated of 31.10.2018 09:00 totalling to 2 125 208,00 RUB (price excl. of VAT)
Обоснование: Признать победителем запроса предложений участника, набравшего наибольшее количество балов, ОАО "Янтарьэнергосервис"(0,003 бала), признать вторым по ранжиру ООО "ПЭС", набравшему 0 балов.