The right to enter into an Agreement for the commissioning of electrical equipment: TTO and SRW 20UKT storage buildings; 20UJE steam chamber buildings; buildings of the auxiliary building 20UKA during commissioning of Unit 2 of the Belarusian NPP
The right to enter into an Agreement for the commissioning of electrical equipment: TTO and SRW 20UKT storage buildings; 20UJE steam chamber buildings; buildings of the auxiliary building 20UKA during commissioning of Unit 2 of the Belarusian NPP Выполнение пусконаладочных работ электротехнического оборудования: здания хранилища ТТО и ТРО 20UKT; здания паровой камеры 20UJE; здания вспомогательного корпуса 20UKA при вводе в эксплуатацию энергоблока № 2 Белорусской АЭСCollapse
Purchasing items:
1.
Выполнение пусконаладочных работ электротехнического оборудования: здания хранилища ТТО и ТРО 20UКТ; здания паровой камеры 20UJE; здания вспомогательного корпуса 20UKA при вводе в эксплуатацию энергоблока № 2 Белорусской АЭС (1 B17), Price: 29 504 231,39 RUB(price excl. of VAT: 24 586 859,49 RUB) per unit
1. Цена договора;
2. Наличие действующей системы менеджмента качества, подтвержденной сертификатом соответствия Системы сертификации РОСАТОМРЕГИСТР.
Possibility of holding a rebidding:
Yes
Contract conclusion date:
06.05.2020
Документация по лоту:
Not uploaded
Payment terms:
According to the draft agreement
Delivery terms:
Republic of Belarus, Grodno region, Ostrovets district, construction site of power units No. 1.2 of the Belarusian NPP.
Date and time of bids evaluation:
31.03.2020 23:59
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Bid documentation provision procedure:
Bid documentation in electronic form is available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date a call for bids is published.
Bid security
Security amount:
Required application security in the amount of 147000.00 rubles
Currency:
RUB
Security form:
Monetary funds, Irrevocable bank guarantee
Contract performance security
Security amount:
A contract enforcement of 5.00% is required. The term for the provision after the conclusion of the contract, no later than 20 days from the date of its conclusion
Security form:
Monetary funds, Irrevocable bank guarantee, Surety or independent guarantee
Security
Security amount:
Требуется обеспечение исполнения гарантийных обязательств в размере 5.00%
Currency:
руб.
Security form:
Monetary funds, Irrevocable bank guarantee, Surety or independent guarantee