The right to conclude a contract for the execution of works "dismantling of the buildings of Bereznikskaya CHP-2" for the needs of the branch "perm" PJSC "t Plus" (PP Bereznikovskaya CHP-2) (569/19)
The right to conclude a contract for the execution of works "dismantling of the buildings of Bereznikskaya CHP-2" for the needs of the branch "perm" PJSC "t Plus" (PP Bereznikovskaya CHP-2) (569/19)
Procurement method (according to the procurement regulations):
Открытый запрос предложений в электронной форме
OKPD2 category:
43.11 Работы по сносу зданий и сооружений
OKVED2 category:
43.9 Работы строительные специализированные прочие
Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:
1. For participants in the SMSP:
Payment of the contract price (performed works) is made by the customer on the basis of the agreement signed by the parties on the completion of work on the object, with a delay of not more than 30 (thirty) calendar days from the date of signing the act of acceptance of completed Work, provided the contractor delivers the complete set of the following documents to the customer:
o Account
o Act of Acceptance of completed works (Form № KS-2), signed by the parties;
o References on the cost of work performed and costs (Form № KS-3), signed by the parties;
o Invoice.
Settlements under the agreement are made by transfer of funds to the current account of the contractor, specified in the agreement, and may have a different form of settlements, not contradicting the legislation of the Russian Federation.
2. For non-SMSP participants:
Payment of the contract price (executed works) is made by the customer on the basis of the agreement signed by the parties on the completion of works on the object, with a delay of not less than 60 (sixty) and not more than 90 (ninety) calendar days from the date of signing the Act Acceptance of the completed works, provided the contractor submitted the complete set of the following documents to the customer:
o Account
o Act of Acceptance of completed works (Form № KS-2), signed by the parties;
o References on the cost of work performed and costs (Form № KS-3), signed by the parties;
o Invoice.
Settlements under the agreement are made by transfer of funds to the current account of the contractor, specified in the agreement, and may have a different form of settlements, not contradicting the legislation of the Russian Federation.
Delivery terms:
Terms of work execution: 01.08.2019-30.11.2019
Venue of bids examination:
614990, Россия, Пермский край, г. Пермь, Комсомольский пр,48
Date and time of bids consideration:
28.06.2019 12:00
Results date and time:
08.07.2019 12:00
Georeferencing:
Russia, Perm Krai, 618421, Zagorodnaya str.
Comments: 1. Place of Take stock totals: 614990, Russia, Perm region, Perm, Komsomolskiy Ave., 48.
2. The obligations of the participants of the request for proposals related to the submission of proposals shall be provided with a penalty of 2% of the initial (maximum) price of the contract (including taxes). If the initial (maximum) price of the contract does not exceed five million rubles the requirement to ensure the application for participation in the purchase is not established.
3. The organizer of the request for proposals may conduct the procedure of price regulation.
4. The winner of the request for proposals will be chosen by the participant, who offered the best technical and economic conditions in accordance with this notice.
5. The Agreement on the results of the OZP shall be no earlier than ten days and not later than twenty days from the date of placement in the EIS of the final protocol drawn up by the results of the OZP.
6. If necessary, the customer has the right to extend the deadline for the acceptance of proposals, established in the notice of request for proposals with the notification of all participants.
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:
Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
The Organizer has announced the results on 05.07.2019 at 07:41
and selected the winner: ООО "Уралстройсервис" – (Bidder 6) (Алексеев Я.В.) submitting a bid dated of 01.07.2019 13:41 totalling to 3 228 000,00 RUB (price incl. VAT)
Notifications have been sent to bidders.
On-line Rebidding No.1 is held on 01.07.2019 at 14:11