Request for Proposals No. 3263800 
Design and installation of fire protection of steel structures and ensuring the required fire resistance Yekaterinburg

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
96.01.12.200  Прочие услуги при химической чистке
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:29.03.2023 16:00
Last edited:22.03.2023 10:12
Bidding cancellation date:22.03.2023 17:32
Organizer (Initiator):OOO "VB DEVELOPMENT"
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing the total lot price from their previously submitted proposal.
:
1% of total amount
Auto-extension
If within the last 10 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 10 minutes from the time the last bid is submitted.
:
10 minutes
Payment terms:post-payment
Delivery terms:7. Scope of work The scope and list of work includes, but is not limited to, the composition
listed below. The work is carried out by the Contractor in full,
"turnkey", by the Contractor's forces, means and mechanisms, including all
necessary consumables and related expenses.
1. Analysis of the KM section, development of a fire protection project for steel
building structures, selection of fire-retardant composition and thickness to
ensure the required fire resistance limits of metal structures, calculation
of the reduced thickness of the metal and the areas of the covered elements,
coordination of the project with the Ministry of Emergency Situations of the Russian Federation, obtaining an expert opinion.
2. Purchase and delivery of materials, consumables, fasteners and other
materials necessary for work.
3. Mobilization of all necessary equipment and tools
to the work site, in the amount necessary for high-quality performance
of work in accordance with the GPR.
4. Input control and quality control of materials with an entry in the journal and
certificates.
5. Warehousing, moving and lifting of materials to the place of
work.
6. Preparation of surfaces and installation of fire-resistant coating
of metal structures, coordination and delivery of completed works with the Ministry of Emergency
Situations of the Russian Federation, obtaining the Conclusion of the Ministry of Emergency Situations of the Russian Federation.
7. Stage-by-stage delivery of works, executive documentation and conclusions
to the Customer's technical supervision representative.
8. other work necessary for the successful completion of the work.
9. Demobilization.
According to the Customer's decision, part or the full volume of materials
listed in the Statement of Work Volumes can be delivered
By the customer, as a tolling material. The obligation, in this
case, for entrance control, acceptance, unloading, moving to the place
of work, lifting, completeness, protection and safety of material
and property, etc., remains with the Contractor.
Georeferencing:620000, Russia, Sverdlovsk region, Yekaterinburg
Comments:
7. Scope of work The scope and list of works includes, but is not limited to, the composition
listed below. The works are carried out by the Contractor in full,
"turnkey", by the Contractor's forces, means and mechanisms, including all
necessary consumables and related expenses.
1. Analysis of the KM section, development of a fire protection project for steel
building structures, selection of fire-retardant composition and thickness to
ensure the required fire resistance limits of metal structures, calculation
of the reduced thickness of the metal and the areas of the covered elements,
coordination of the project with the Ministry of Emergency Situations of the Russian Federation, obtaining an expert opinion.
2. Purchase and delivery of materials, consumables, fasteners and other
materials necessary for work.
3. Mobilization of all necessary equipment and tools
to the work site, in the amount necessary for high-quality performance
of work in accordance with the GPR.
4. Input control and quality control of materials with an entry in the journal and
certificates.
5. Warehousing, moving and lifting of materials to the place of
work.
6. Preparation of surfaces and installation of fire-resistant coating
of metal structures, coordination and delivery of completed works with the Ministry of Emergency
Situations of the Russian Federation, obtaining the Conclusion of the Ministry of Emergency Situations of the Russian Federation.
7. Stage-by-stage delivery of works, executive documentation and conclusions
to the Customer's technical supervision representative.
8. other work necessary for the successful completion of the work.
9. Demobilization.
According to the Customer's decision, part or the full volume of materials
listed in the Statement of Work Volumes can be delivered
By the customer, as a tolling material. The obligation, in this
case, for entrance control, acceptance, unloading, moving to the place
of work, lifting, completeness, protection and safety of material
and property, etc., remains with the Contractor.
8. Initial
data provided

Appendix A: Statement of work volumes
Appendix B: A set of Working documentation. KM1, KR
Appendix B: Schedule of work.
by the customer
9. Requirements for
the
work
1. The company must have the appropriate licenses and permits to
carry out activities for the design and execution of works on
fire protection of structures.
2. Calculate the reduced metal thickness of the elements
of metal structures that require
fire resistance limits.
3. Calculate the fire resistance limits of unprotected elements
of metal structures.
4. Perform the calculation of the areas of protected elements of metal
structures, coordinate with the General Designer.
5. Prepare a summary table with an indication for each element –
Required fire resistance limit, PTM, fire resistance limits
of an unprotected element, protected area, dry layer thickness, consumption
per m2, total consumption.
6. To coordinate the project of fire protection of steel building structures with
The customer and the General Designer, after that with the Ministry of Emergency Situations of the Russian Federation.
7. Before the start of the work, coordinate the PPR and a detailed schedule
of work with the Customer.
8. Notify the manufacturer of metal structures about the list and
requirements for the painting of metal structures subject to fire protection.
9. Perform cleaning and preparation of the surfaces of the protected MK, according
to the requirements of the manufacturer of the flame retardant material, the requirements
of the fire protection project, PPR.
10. Preparation of surfaces and installation of fire-resistant coating
of metal structures, to be presented in stages and handed over to a representative
of the Customer's technical supervision. The completed works should be approved and handed over
IPL OF THE Ministry OF Emergency Situations of the Russian Federation.
11. All work is carried out "turnkey" with materials and by the Contractor.
The cost of the work includes, temporary lighting, a wheel washing point and its
maintenance and accommodation and meals for personnel, the construction of temporary
roads, networks and structures, sanitary facilities and their
maintenance, maintenance and maintenance of the work site and
approaches to it, consumables, overlaps, overlaps and docking
materials, travel expenses, materials and equipment for
laying, maintenance and heating of concrete, personal protective
equipment for safety, snow cleaning, drainage, collection, removal and disposal
of garbage, safety of materials, equipment and property, obtaining and
developing the necessary accompanying documents for the production of works
and other costs necessary for the successful completion of work within
the time limits set by the contract and with the quality corresponding to the requirements of the Customer, this TOR and Working Documentation.
12. When constructing an object, follow the RD-11-02-2006 regarding
the composition and list of acts of inspection of works and inspection
of structures, a set of Executive documentation.
13. When performing work and after completion of work, it is necessary to
clean the territory and remove garbage.
14. Any changes in the composition and content of the work, the
equipment and materials used are documented in writing
and sent to the Customer for consideration.
15. Payment for the work performed is made for
the amount of work actually performed, on the basis of executive documentation, with confirmation
by technical supervision and a surveyor of the customer. The volumes and cost
of the work performed are closed "in the body", i.e. taking into account the coefficient of compaction,
decompression, spills, losses during transportation and during
unloading / loading, overlaps, scraps, overlaps, coefficient for
irreparable losses, coefficient of metal deposition, etc. should be
included in the cost of work.
16. The Contractor undertakes to prepare and send to the Customer a daily
report, according to the Customer's form, on the work performed.
10. The list
of normative works should be carried out in accordance with the requirements of the regulations:
Federal Law No. 123 of 22.07.2008. Technical regulations on the requirements of fire
technical
documents, in
accordance with
the requirements
of which
it is necessary
to perform
work
GOST R 53295-2009 Fire protection equipment for steel structures. General requirements. Method for determining the flame retardant effectiveness. SP 2.13130.2020 Fire protection systems. Ensuring
fire resistance of protection objects.
SP 4.13130.2013 Fire protection systems. Limiting
the spread of fires at protection facilities. Requirements for space planning and design solutions.
in force on the territory of the Russian Federation, Working documentation, Statement
of work volumes, Contract and this Technical Specification, other
technical and regulatory documents;
The materials, equipment, tools used must
comply with GOST, technical specifications applicable in the territory of the Russian Federation, have
the necessary certificates and permits
11. Guarantee for the
result of the work
The guarantee for the result of the work performed by the Contractor is 5 years.
12. Requirements
for occupational

health and safety.
The contractor is obliged to strictly comply with the requirements of OT and TB, in
accordance with the requirements of Russian legislation, as well
as the internal requirements of the enterprise when carrying out work. The Contractor
is obliged to respond immediately to all comments from the Customer
on violations of the rules of OTiTB, and immediately eliminate such comments.
The customer has the right to stop the contractor's work until
the violations are eliminated, if such violations can lead to serious
injuries or death of the contractor's employees. The Customer has the right to impose a fine
on the Contractor for not fulfilling the Customer's requirements to eliminate violations
of the OTiTB rules.
13. Temporary
roads and access to
the place of
work.
Access and on-site entrances to the places of work
are organized
14. Provision
of electricity
The customer provides a connection point in the construction site area
15. Provision
of water supply
The contractor independently provides its needs for technical and
household water supply.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.

Organizer has decided to cancel the call for bids.
Call for bids cancellation date: 22.03.2023 at 17:32.
call for bids cancellation reason:

будет корректировка ТЗ

Total bids: Hidden