Request for Proposals No. 2706767 
Overhaul of 4 Section 1 Direct Heating Furnace No. 1 (Kastner) of CGE Section 2, In.No. 1266, with Exhibit foundation plate and SCP.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:15.07.2021 15:32 (was extended by 32 min, 14 sec)
Last edited:01.07.2021 14:54
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Monthly, within 30 (thirty) bank days after the performance is delivered, provided that the work is done properly and within the agreed time frame. The work is considered to have been completed following the signing of the Acquires of Work (Form COP-2) by Parties and the Certificate of Cost of Work Performed and Cost (Form COP-3).
Delivery terms:1. General information about EPM - Novocherkassky Electrode Plant
1.1. Organizational and legal form Open Joint Stock Company
1.2. Legal address 346413 - Russian Federation, Rostov region, Novocherkassk city, Aluminum playground
1.3. Actual address 346413, Russian Federation, Rostov region, Novocherkassk city, Aluminum playground
1.4. Bank details, INN 6150003065
1.5. RCEA Code 26.82.4 Production of Artificial Graphite
1.6. F.I.O., Head position: Sergei Yelkov - Manager
director.
1.7. F.I.O., post, telephone, fax of the official responsible
Technical condition of equipment: Roman Dinkov - Technical Director,
Tel 8 (8635) 29-48-11, fax 8 (8635) 29-48-23.
1.8. F.I.O., post, telephone, fax of the official responsible
repair: Oleg Martyshchenko - Chief Mechanic.

Tel 8 (8635) 29-48-24, fax 8 (8635) 29-42-55, e-mail: OMartischenko@energoprom.ru

2. Place of work: Customer's territory (EPM-NEZ JSC).
3. Object (technical device)
Periodic industrial furnace for gaffiting fired blanks. The panel-frame furnace is conventionally composed of 3 parts: an air exhaust system, a monolithic w/b foundation with channels, grooves and notches, and an overhead part of 4 halves.
4. Purpose of the work:
Conduct restoration of all furnace elements — the subdin,
ends, side and intermediate walls made of reinforced concrete blocks, as well as reigniting
foundation plate and SCP
5. List and volume of work carried out:
5.1. Refractory work and construction work — hell. PH 09803 SAT, ST (PH) 13621 KJ
5.2. Work to repair the steel structures of the furnace, hydraulic system, and pressure devices is a heck. PH 09803 SAT, ST (PH) 13621 KJ, PH 03305.35.01 SAT, PH 13222 SAT, TH 13222, NS 08516.01.03, NS 08516.01.02, NS 08516.01.06 SAT, NS 08516.01.01.04, NS 0312034, NS 08516.01.05A, NS 08516.01.19, NS 08516.01.20, PH 04203.01.04, PH 04203.01.05 PH 13222.250 RM 03331.04 NS 04.969.04.00-01.
6. Apps: Technical documentation (drawings) - damn. PH 09803 SAT, ST (PH) 13621 KJ, PH 03305.35.01 SAT, PH 13222 SAT, TH 13222, NS 08516.01.03, NS 08516.01.02, NS 08516.01.06 SAT, NS 08516.01.01.04, NS 0312034, NS 08516.01.05A, NS 08516.01.19, NS 08516.01.20, PH 04203.01.04, PH 04203.01.05 PH 13222.250 RM 03331.04 NS 04.969.04.00-01.
7. Performer Requirement:
7.1. Overhaul of 4 Section 5 Direct Heating Furnace (Kastner) Section 1
CGE, with the design position and the strengthening of the SCP and UPR. — from the Customer's material
7.2. Working under a current enterprise. The business hours are 24 hours a day.
7.3. Possible exposure to harmful factors: dustiness, gas
7.4. Develop PPR and process maps for all necessary work.
7.5. The executor must have the necessary production and human skilled
resources to do this work. Have the certification of a supervisor, ITR and workers
industrial safety, copies of contracting documents
occupational health service and/or occupational health professional (order on
appointment
to a position in a contracting organization, occupational safety certificate) or
having a contract with an accredited organization in the area of occupational health services
also having a medical clearance
7.6. Availability of SRO for these types of work.
7.7. The availability of machines and mechanisms to carry out the entire range of work.
7.8. Performer personnel must have and use personal protective equipment.
7.9. In case of comments to staff on quality of work performed, disruption
security, as well as administrative violations, on demand
Customer specialists The Contractor is required to replace these workers immediately.
7.10. The work not performed should be redone at the expense of the Contractor and surrendered
The customer.
7.11. Employees are placed in this work by the Contractor.
Customer, subject to availability, can place workers on the Contract
basis.
5.12. Design and approval of linear furnace repair schedules.

8. Payment Terms: Monthly, within 30 (30) Bank Days After Delivery
performance provided that the work is done properly and within the agreed time frame. The work is considered to have been completed following the signing of the Acquires of Work (Form COP-2) by Parties and the Certificate of Cost of Work Performed and Cost (Form COP-3).
9. Duration: 01.09.2021 — 26.10.2021 (40 working days). The commencement of work is agreed with the Customer further.

10. Work warranty: 24 months from completion of work, for each of the refurbishment facilities.

11. The transfer to repair and reception of equipment from repair is carried out in accordance with the EPM-NEZ regulations approved by JSC.

12. The furnace is repaired in the operating shop. The repair schedule is coordinated with the workshop (CGE) and plant services (UM, EU).

13. List of documents provided to the EgoICHS OTPB for work permits by contracting organizations:

Contractor is required to provide prior to the clearance of the work
The following documents to the customer:

1. a copy of the certificate (SRO) for the right to perform this type of work;
2. copies of documents confirming the presence of a service in the contracting organization
occupational health and/or occupational health professional (appointment order in
contracting organization, occupational safety certificate) or availability
contracts with an accredited organization in the field of occupational health services;
3. a copy of the occupational health briefing from the briefing log;
4. ERP or PPR or RTI;
5. a copy of the Occupational Safety Workers' Certification Protocol;
6. copies of ITR Health and General Requirements Certification
industrial safety. When performing gas work, on vessels operating
pressurized, with GPM, electrical installations, firing
7. copies of the certificates for each type of work;
8. staff medical clearance;
9. copies of the certificates of gas welders, rafers, cranes machinists,
lifts (towers). For electric gas welders, copies of the certification protocols
PTM.

Contractor shall notify Customer in writing of all these conditions
form with the appendix of all supporting documents. Failure to comply
of this paragraph, Contractor entitles the Customer to prevent Contractor from
work, overdue work in such a case is the fault
Contractor.


14. Note:
- Shipping material from the warehouses of JSC EPM-NEZ to the site of the work, the removal of debris (non-scaffolded firebricks, graphite, scrap metal, etc.) to storage sites located on the territory of JSC EPM-NEZ is carried out by the Executor transport.
- Trash collection of all categories to industrial waste landfills outside EPM-NEZ JSC (garbage collection from 7km to 30km) is carried out by transport provided by the Customer, upon the Contractor's prior request.
- All categories of garbage disposal costs, industrial waste landfills,
located outside EPM-NEZ JSC are at the expense of the Customer.
- The bridge cranes for furnace are provided by Customer, bridge machinist
The Crane is provided by the Performer.
- Work in a working shop. It is forbidden to carry out repairs on the furnace if the standing furnace nearby is in the company (the process of graphitation of the blanks) plus eight hours after the company ends next to the standing furnace.
Georeferencing:Russia, Rostov region,
Comments:
The participant who has taken part in the procedure (making an offer) is required to upload the following documents to the system before the deadline for the application deadline:
1. Charter (with all additions and modifications if there were any).
2. Certificate of State Registration.
3. Tax Accounting Certificate.
4. Extract from EGRUL.
5. The balance sheet as of the latest reporting date with the tax authority's acceptance mark.
6. Documents confirming the representative's signature credentials:
— Decision (Protocol).
— Power of attorney.
7. Proposal for work (see Proposal file)
8. Contact: Maxim Prasnick — Head of Production Modernization
Tel 8 (8635) 29-48-236, email: MNaprasnik@energoprom.ru
Oleg Martyshchenko - Chief Mechanic.
Tel 8 (8635) 29-48-24, fax 8 (8635) 29-42-55, e-mail: OMartischenko@energoprom.ru
9. ISO 9001:2008 Certificate of Compliance (if available)
This request is not a notice of a contest or auction and does not give any rights to the participants, and does not entail any duty other than expressly specified in the notice.
10. Performer Requirements:
— Permissive documents (SRO, licenses, tolerances)
— Development by the PPR, PRC, RTI.
— Certification of supervisor, ITR, industrial safety workers at the GOPO.
— Medical admission of staff to work at GOPO.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 29.07.2021 at 07:12
and selected the winner: OOO "OSNOVA" – (Bidder 4) (Устименко Н.В.) submitting a bid dated of 15.07.2021 15:02 totalling to 18 000 000,00 RUB (price excl. of VAT)
Notifications have been sent to bidders.
Total bids: 4. More >>