Carrying out works on the reconstruction of production facilities 1. Project development:
- Designing sections for project implementation
2. Carrying out works:
- Dismantling/ installation work;
3. Project management:
- Project management and maintenance.Collapse
OKPD2 category:
Show all (0 more)
42 Сооружения и строительные работы в области гражданского строительства
42.9 Сооружения и строительные работы по строительству прочих гражданских сооружений
42.91.20.190 Работы строительные и ремонтные, связанные с прочими водными сооружениями и работы по ремонту всех вышеуказанных сооружений
Bidders can submit a bid for separate items within the call for bids
:
Applicable
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Ranking of bids
In the course of bidding, a price-based rank (position) shall be assigned to a quotation.
Assignment of the 1st rank (position) to a bid does not imply the bidder's winning, but enhances the bid's preferability for the Buyer when selecting the winner, all other factors being equal.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
In calls for bids with bids ranking, bid submission deadline will automatically be extended in the same manner if the rank of a bidder changes.
:
30 minutes
Payment terms:
30% prepayment;
20% after acceptance of stage 1;
50% after acceptance and completion of stage 2 and signing of general closing documents under the contract.
Delivery terms:
Terms of the project based on the completion of the stages of work:
Stage No. 1 until 08/31/2024 (premises №: 1, 4, 5, 6, 7, 8, 9, 16)
Stage No. 2 until 12/31/2024 (premises №: 2, 3, 10, 11, 12, 13, 14, 15, 17, 18, 19, 20, 21, 22, 23)
Georeferencing:
117403, Russia, Moscow, Nikopolskaya str., 4
Comments: 1. Experience in performing similar work for at least 15 years
2. The Contractor company must be registered and have its office in Moscow or Moscow region
3. A prerequisite:
- The contractor must be a member of a self-regulating organization (Confirmed by an extract from the register of SRO members in the form approved by Rostechnadzor Order No. 86 dated 03/04/2019). Provide a supporting document;
- The contractor must have at least 10 IT in the company's staffing table (Engineering and Technical worker). Provide a supporting document;
- The contractor must have in the staffing table of its employees included in the register of specialists NOSTROY (LDC - National Association of Builders). Provide a supporting document.
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:
Мы будем рады ответить на ваши вопросы и предоставить дополнительную информацию, если это необходимо в разъяснениях тендера, спасибо!
Также можете обращаться на почту:
�i.boiko@faberlic.com