Request for Proposals No. 2412219 
Repair of 0.4 kV cable lines at EPM-NEZ JSC in 2020

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Repair of 0.4 kV cable lines at EPM-NEZ JSC in 2020

OKPD2 category:
42.22.2  Работы строительные по строительству коммунальных объектов для электроснабжения и телекоммуникаций
42.22.21.110  Работы строительные по прокладке линий электропередачи значительной протяженности над землей, включая линии для железных дорог, и по их ремонту
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:29.07.2020 18:48 (was extended by 1 h, 48 min, 32 sec)
Last edited:15.07.2020 14:00
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Upon completion of work
Delivery terms:1. Application of EPM-NEZ JSC Novocherkassk.

2. Purpose of work

Replacement of 0.4 kV cables laid open on the overpass and broken during operation to ensure reliable power supply to the fire-fighting pumping pump, from the material of the contractor.

3. Deadline

Start of work July 2020
Completion of work August 2020.

4. The contents of the repair work

4.1. To dismantle the failed cable lines from TP 19 to SP-1 of fire-fighting pumping and from TP 19A to SP-2 of fire-fighting pumping.

4.2. To lay two strands of the AVVG 4x70 cable route (multi-core) from TP 19 to SP-1 of a fire-fighting pumping station and from TP 19A to SP-2 of a fire-drinking pumping station along the existing cable overpass, 250 meters each.
4.3. Disconnect the cable lines in TP 19, TP 19A, SP-1 and SP-2 fire-fighting pumping station.
4.4. Lifting mechanisms for dismantling and installation, equipment, tools, mechanisms for loading and unloading are provided by the Contractor. Motor vehicles for the removal of garbage, scrap metal or other waste are provided by the Contractor.
4.5. Electric welding, gas cutting equipment, consumables are provided by the Contractor.

5. Requirements for the Contractor

5.1. The contractor must have the necessary production and human resources to carry out this work, be a member of a self-regulatory organization (SRO).

5.2. To clarify the conditions of work, familiarization with the object is desirable
arrival of representatives of the Contractor to the Customer.

5.3. The contractor in his commercial proposal indicates the payment procedure
and other conditions.

5.4. Certification of the head, engineers and industrial safety performers and
labor protection at the OSE in accordance with Appendix No. 1.

5.5. Provision of HSE measures, safe methods of work at the facility.

5.6. After completion of work, the contractor transfers the executive
documentation according to RD-11-02-2006 dated 12/26/06. and other regulatory documents.

5.7. Warranty coverage for at least 24 months.
Employees involved in the performance of work must have professional training corresponding to the nature of the work with a mark on the special certificate of training and exams in the certification commissions.

6. Work safety

When performing repairs, the contractor must comply with the following rules:
- Rules for labor protection during the operation of electrical installations;

- Rules for the technical operation of electrical installations of consumers;

- Safety rules for hazardous production facilities that use lifting facilities;

- Rules for the installation of electrical installations;

- Fire safety regulations;

- Rules for labor protection when working at height POT RM-012-200;

- The rules of environmental, sanitary and hygienic and other standards in force in the Russian Federation and to ensure safe working conditions for human life and health.

To perform the work, the contractor must undergo an introductory briefing. All work performed on the territory of EPM-NEZ JSC must be carried out in accordance with the provision "On the use of tolerance orders in the work of increased danger at EPM-NEZ JSC".
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
The participant who participated in the procedure (made an offer), before the deadline for accepting applications, is obligated to upload the following documents to the system:
1. Articles of Association (with all the amendments, if any).
2. Certificate of the state registration.
3. Certificate of tax registration.
4. Extract from USRLE.
5. Balance sheet as of the last reporting date with tax authority stamp of acceptance.
6. Documents confirming the powers of the person authorized to sign the documents:
— Decision (Protocol).
— Power of attorney.
7. Proposal for work (see file "Proposal for work")
8. Contact persons:
Deputy Chief Power Engineer for Electrical - Vitaliy Fateev
tel. 8 (8635) 29-44-83 VFateev@energoprom.ru
9. Certificate of compliance with the requirements of the standard ISO 9001: 2008 (if available)
This request does not constitute a notification of tender or auction and shall not grant any rights to the participants and shall not entail any obligations except those explicitly stated in the announcement.
10. Requirements for the Contractor:
- Permitting documents (SRO, licenses, admissions).
- Development by the executor of PPR, PPRK, RTI.
- Availability of certification of the head, engineers, industrial safety workers at the public educational institution.
- The presence of medical admission of personnel to work at the public educational institution.
—Before the execution of the work permit permit, the Contractor is obliged to provide the Customer with the following documents: copies of documents confirming that the contractor has a labor protection service and / or labor protection specialist (order of appointment to the contractor, certificate of labor protection specialist) or the presence of a contract with an accredited organization in the field of labor protection services.
For consideration of the application it is MANDATORY to provide a commercial offer.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 19.08.2020 at 08:40
and selected the winner: "RES" OOO – (Bidder 2) (Тумко Н.Н.) submitting a bid dated of 29.07.2020 18:18 totalling to 300 000,00 RUB (price excl. of VAT)
Notifications have been sent to bidders.
Total bids: 2. More >>