Repair of umbrellas and cover of CGE furnaces
See the technical assignment with accompanying documentation (Complex service)

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:07.10.2021 12:00
Last edited:23.09.2021 16:32
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:11. Payment Terms:
11.1. Payment is made after the actual work is done.
11.2. Payment is made by cashless payment by transferring money to the Contractor's current account.
11.3. The cost of repairing m/to the umbrellas and cover covers of the graphitation furnaces specified in the "Pe River of Operated Umbrellas and Graphitation Furnace Cover" shall be based on the requirements of the "Performer" ; in its offer, rates (Appendix 4)
11.4. The cost of disposing m/k of graphitation furnace umbrellas and cover covers specified in the "List of operated graphitation furnace umbrellas and cover covers" is based on the proposed "Performer" in its offer, rates (Appendix 5), with the physical amount of disposal of the umbrellas and covers of the graphification furnace shelter under the contract being adjusted as a matter of fact work carried out by the two - party agreement of the "Parties".
11.5. Payment amount is made up of invoice amounts, work performed
Delivery terms:1. EPM-NEZ JSC application, St. Novocherkassk.
2. Purpose of works:

Collection and removal of waste gases from the CGE furnaces of Section No. 1, 2,8,10.

3. Scope of work carried out:

Repair of the umbrellas and cover covers of the graphitation furnaces specified in the list, with removal to the repair site and entry to the workshop at the end of the repair.
3.1. List of Graphitation Furnace Umbrellas and Shelter Cover Operated
- section 1 - 4 umbrellas
- Cover section 2 - 4;
- Section 2, Furnace 5, 5A - 2 covers;
- section 8 - 2 umbrellas
- section 10 - 4 umbrellas.

3.1.1. Repair m/k of furnace shelter umbrellas:
- damn. NS 12529 Sat; NS 12549 Sat; NS 12572 Sat; NS 13329 Sat; NS 12635 Sat; NS 05569.01 Sat — Annex 2 TK.

3.2. Furnace shelter covers m/k repair:
- damn. NS 12911 Sat; NS 10056.01 Sat; NS 10056.02 Sat — Annex 3 TK.




4. Requirements for the Contractor.

4.1. The contractor must have all the necessary production and human resources to carry out the job.
4.2. In order to clarify the conditions for the work and to get acquainted with the object, the Contractor's representatives will come to the Client.
4.3. The Contractor specifies the payment procedure and other terms and conditions in its offer.
4.4. Appendix 1 certification of the supervisor, ITR and occupational safety and health executors at the GCSEs.
4.5. Provide OT and PB measures with safe on-site operations.
4.6. In case of reasonable comments to the staff on the quality of the work performed, safety violations, as well as administrative violations, as required by the Client's specialists, the Contractor must replace the work data immediately.
4.7. The work that has not been done in good quality must be redone at the Contractor's expense and delivered to the Customer.
4.8. Placement in sanitary premises of workers employed for this work is performed by the Contractor. The customer, if available, can arrange for workers to be placed on a Contractual basis.
4.9. The Contractor shall develop and agree with the Customer the estimates, the linear schedule of the work, the erp, the PPR and the process maps for all necessary work — within a period of not more than 15 calendar days after declaring the winner of the competition procedure.
4.10. It is necessary to have SRO for these types of work.


5. Work conditions

5.1. Working at an operating company.
5.2. The works are made from the Customer's materials.
5.3. The Contractor provides lifting mechanisms and mechanisms for handling and unloading, and a trans port for the work.
5.4. Electric welding and gas cutting equipment is provided by the Contractor.
5.5. The consumables for electric welding and gas cutting equipment are provided by the Contractor.
5.6. Vehicles for removal of scrap metal or other waste are provided by the Contractor.

6. Place of work:

6.1. Customer and Contractor Territory.

7. Deadlines:
7.1. Within a year of the conclusion of the contract.

7.2. To proceed with repairs within 5 working days from the date of receipt of the written request from the Customer, and submit them to the Customer under the Acceptance Act within 15 working days at the latest days


8s. Payment Terms:
8.1. Payment is made after the actual work is done.
8.2. Payment is made by cashless payment by transferring money to the Contractor's current account.
8.3. The cost of repairing m/to the umbrellas and cover covers of the graphitation furnaces specified in the "Pe River of Operated Umbrellas and Graphitation Furnace Cover" shall be based on the requirements of the "Performer" ; in its offer, rates (Appendix 4)
8.4. The cost of disposing m/k of graphitation furnace umbrellas and cover covers specified in the "List of operated graphitation furnace umbrellas and cover covers" is based on the proposed "Performer" in its offer, rates (Appendix 5), with the physical amount of disposal of the umbrellas and covers of the graphification furnace shelter under the contract being adjusted as a matter of fact work carried out by the two - party agreement of the "Parties".
8.5. The amount of payment is made up of invoices and works performed.


9. Mandatory requirements and conditions for entering into a contract:

9.1 In the case of the contracting organization's staff (including staffing and number of employees under civil law contracts of a character) of less than 10 (10) persons, the contractor's co-driver is obliged to submit, in two copies, an appeal containing a roll - call list prior to the commencement of work under the contract personnel who are expected to perform the work under the contract. Copies of civil passports and employment contracts (or pre-agreements of a civil nature) signed with the persons in question must be attached to this request.
9.2. As a result of the work under the contract, the contractor, together with AC-Volume KS-2, provides the customer with copies of the report of the Form NW-M "Information on Insured Persons" and a positive report entry control on the transfer of the report to the territorial authority of the Pension Fund of Russia, signed by the EPC for the period of time specified in the document of Form COP 2 submitted by them.
9.3. In the event of failure to provide the NW-M reports, or if there is a discrepancy less than the number of contractor's employees as indicated in the previously submitted request, acts KC-2 are not signed by the customer, and the parties to the contract acknowledge that the contractor has not performed the work, and the work is not payable under these acts.


10s. General Requirements:

10.1. Prior to the tender, the contractor provides:

- Certificate of approval for a certain type of work that has an impact on the safety of capital construction facilities (SRO certificate for the work specified in this Assignment).




Annex 1

List of documents provided to the OTIP for the issuance of work permits by contractors:
1. Copy of Certificate (SRO) for the right to perform this type of work
2. Copy of the occupational health briefing from the Instruction Journal, ERP, PPR or RTI.
3. Copy of the Workers' Occupational Safety Certification Report.
4. Copies of ITR certification certificates for occupational health and general industrial safety requirements. When performing gas work, pressure receptacles using GPMs, lifts (towers), electrical installations, fire works, copies of certificates for each type of work.
5. Staff medical clearance.
6. Copies of certificates of gas-electric welders, slingers, cranes, hoists (towers). For gas-electric welders - copies of fire and technical minimum certification reports.
7. Prior to the issuance of a work permit, the Contractor must provide the Customer with the following documents: copies of documents confirming occupational safety and/ or occupational safety specialist (appointment order, occupational safety certificate) or a contract with an accredited organization in order to provide occupational health services.
8. All contractors, including managers, are required to undergo an induction training at the OTIP (carry identity and age documentation) prior to the start of the permit. all employees must have certified clothing, footwear and other personal protective equipment required for this type of work.


Note: If any document expires, the clearance will not be issued until the new document is submitted.
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
The participant who participated in the procedure (who made the offer) must upload the following documents to the system before the deadline for applications:
1. Charter (with all additions and changes, if there were any).
2. Certificate of State Registration.
3. Tax Registration Certificate.
4. Extract from the EGRUL.
5. Balance sheet as of the last reporting date with tax authority acceptance mark.
6. Documents confirming the authority of the representative to sign documents:
— Solution (Protocol).
- Power of Attorney.
7. Proposal for work (see Proposal for Work file)
8. Contact: Chesnokov Alexey Leonidovich, tel. 8 (8635) 29-45-30, e-mail: AChesnokov@energoprom.ru
9. ISO 9001:2015 Certificate of Compliance (if available)
This request does not constitute a notice of competition or auction and does not confer any rights to the participants, does not entail any obligations other than those expressly stated in the notice.
10. Executor Requirements:
— Permitting documents (SRO, licences, permits)
— Development of PPR, PPRK, RTI.
— Certification of supervisor, ITR, industrial safety workers at the GOPO.
— Medical clearance of staff to work at the GOPO.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:Контактное лицо: Чесноков Алексей Леонидович, тел. 8(8635)29-45-30, электронная почта: AChesnokov@energoprom.ru
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 26.10.2021 at 09:17