Request for Proposals No. 1017263 
CMP on the object "reconstruction of the 0.4 kV CL from TSS-13 with the construction of VL-6 kV from Sg-13 and installing the new TP on the Repeater for the needs of" ESY "(the length of the 0.4 kV CL-0.05 km, VL-6kV-1.8 km, 6 kV CL 0.12 km/63/6...

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
43.21.10.290  Работы электромонтажные прочие, не включенные в другие группировки
OKVED2 category:
43.21  Производство электромонтажных работ
Quantity:1 pc; 1
Per unit price:4 143 055,86 RUB (price incl. VAT, VAT: 18%)
Total price:4 143 055,86 RUB (price incl. VAT)
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:30.05.2018 09:00
Last edited:22.05.2018 07:15
Organizer (Initiator):PUBLIC JOINT STOCK COMPANY "ROSSETI VOLGA"
Customers:PAO "ROSSETI VOLGA"
Customer's postal address:410031, г.Саратов, ул. Первомайская, 42/44
Customer's registered address:410031, г.Саратов, ул. Первомайская, 42/44
Contact email address:omon_ma@orene.ru
Buyer's contact phone number:+7 (3532) 79-76-65
Additional info
Call for bids subject to Federal Law No. 223-FZ:Yes
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Hide bid prices during bids submission period:Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Participation of small and medium businesses
Organizer has initiated the bidding only for small and medium businesses to participate. Verification of compliance with the criteria for being qualified as small and medium businesses is to be performed by the organizer.
:
Участниками данной закупки могут быть только субъекты малого и среднего предпринимательства
Payment terms:the current payments are paid by the employer at a rate of 95 per cent of the cost of work stages according to the contract referred to in the instruments of acceptance of the executed works in form of COP 2 and help about the value of work performed and costs form COP-3, within 30 (thirty) calendar days from the date of signing acts of acceptance of works.
Payments on completion of the contract shall be paid within 30 (thirty) calendar days from the date of signing of the Act of putting into operation (acceptance of finished construction project acceptance Committee to form COP-14)
Delivery terms:work start date no later than 7 working days from the moment of signing the contract.
The deadline for the completion of construction and commissioning is no later than 31.10.2018 g.
Deadline for completion of the Treaty is not later 15.11.2018 g
Venue of bids examination:г. Оренбург, ул. Маршала Г.К. Жукова, д. 44
Date and time of bids consideration:22.06.2018 16:00
Results date and time:07.07.2018 12:00
Georeferencing:Россия, 462411, Оренбургская область, г. Орск, ул. Станиславского, 52
Comments:
all the information is in the technical specifications and procurement documentation
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
E-signature info:Signed with e-signature
 
 
 
  Obtain bank guarantee

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
 

Выгрузка на ЕИС

Номер извещения на ЕИС:
31806454328
Results reports
Bids opening results report
Download file Вскрытие.pdf (60 Kb)
Bid evaluation report
Download file Рассмотрение.pdf (250 Kb)
Final results report
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 19.06.2018 at 07:38
and selected the winner: Filial Pugachevskaia MK №99 «OSESS» OOO – (Bidder 3) (Модзелевский В.А.) submitting a bid dated of 29.05.2018 15:04

Download Итоги.pdf (598 Kb)

Notifications have been sent to bidders.
Price / offerCompany / Date Sorted by descending
HiddenOOO "PROMENERGOKOMPLEKS"
(Bidder 4) Kirmenev A.K.
29.05.2018 21:46:07
The best offer
Hidden
Filial Pugachevskaia MK №99 «OSESS» OOO
(Bidder 3) Modzelevskii V.A.
29.05.2018 15:04:37
Hidden"Elektroservis" OOO
(Bidder 2) Khanin A.A.
29.05.2018 14:44:47
Hidden"EnergoStroiInvest" OOO
(Bidder 1) Kurakin D.V.
29.05.2018 10:19:18
Total bids: 4