Request for Proposals No. 1081303 
"Construction of a 10 kV overhead line running from 10 kV overhead line # 7 Tyunyar in the village of Pobeda Village. Tyunyar of Nikolsky district (OOO Aviagen Torkeys Rus) (turnkey) "for the needs of the branch of PJSC" IDGC of Volga "-"...

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
42.22.22.110  Работы строительные по прокладке местных линий электропередачи и связи над землей или под землей
OKVED2 category:
42.22.2  Строительство местных линий электропередачи и связи
Quantity:1 ед
Per unit price:7 989 381,16 RUB (price incl. VAT, VAT: 18%)
Total price:7 989 381,16 RUB (price incl. VAT)
Contract award criteria:Price incl. VAT (show both prices)
Publication date:
Bid submission deadline:07.09.2018 10:00
Last edited:27.08.2018 15:27
Organizer (Initiator):Filial "MRSK Volgi" - "Penzaenergo" OAO
Customers:PAO "ROSSETI VOLGA"
Customer's postal address:410031, г.Саратов, ул. Первомайская, 42/44
Customer's registered address:410031, г.Саратов, ул. Первомайская, 42/44
Contact email address:osipova.en@penzacom.ru
Buyer's contact phone number:+7 (8412) 59-36-77
Additional info
Call for bids subject to Federal Law No. 223-FZ:Yes
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Hide bid prices during bids submission period:Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Participation of small and medium businesses
Organizer has initiated the bidding only for small and medium businesses to participate. Verification of compliance with the criteria for being qualified as small and medium businesses is to be performed by the organizer.
:
Участниками данной закупки могут быть только субъекты малого и среднего предпринимательства
Subcontractors being small or medium businesses must be involved into contract performance
When performing the contract, bidders will be obliged to involve subcontractors (co-contractors) being small or medium business entities.
:
Yes
Payment terms:Payment for the 1st stage (Development of design and working documentation, survey work) shall be paid within 30 (thirty) calendar days after the signing of the Act on the execution of design and survey work for Phase I and invoicing.
The current payments for the second and subsequent stages are paid by the Customer in the amount of 95% of the cost of the stages of work under the contract specified in the acts on acceptance of the executed works in the form of COP-2 (Appendix No. 6) and a statement on the cost of work performed and costs in the form of COP- 3 (Appendix No. 7) shall be paid within 30 (thirty) calendar days from the date of signing the acceptance certificates.
Payments at the end of works under the contract are paid within 30 (thirty) calendar days from the date of signing the act of commissioning (the acceptance certificate of the acceptance commission completed by the construction site, form No. КС-14).
Excess by the Contractor of the amount and cost of works not confirmed by the respective additional agreement of the Parties shall be paid by the Contractor at its own expense provided that they are not caused by the Customer's failure to fulfill its obligations.
Invoices are issued to the Customer by the Contractor in accordance with the legislation of the Russian Federation.
Delivery terms:The period for commencement of works for the first stage shall be no later than 5 working days from the date of the conclusion of the contract. Term of completion of works for the 1st stage - not later than 05/04/2019.
The deadline for the start of work on the II stage is no later than 5 working days from the moment of signing the act on the performance of design and survey works for the I stage.
Term of completion of construction and installation, commissioning - no later than 05/06/19.
The deadline for completion of work under the Agreement is no later than June 10, 2019.
Venue of bids examination:г. Пенза, ул. Пушкина/Гладкова,1/2
Date and time of bids consideration:14.09.2018 10:00
Results date and time:14.09.2018 10:00
Georeferencing:440008 г. Пенза, ул. Пушкина/ул. Гладкова, д. 1/2
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
E-signature info:Signed with e-signature
 
 
 
  Obtain bank guarantee

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
 

Выгрузка на ЕИС

Номер извещения на ЕИС:
31806858543
Results reports
Bids opening results report
Download file Протокол вскрытия.pdf (1.9 MB)
Bid evaluation report
Download file Протокол на переторжку.pdf (3.6 MB)
Final results report
Download file Протокол по выбору победителя.pdf (14.4 MB)
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 14.09.2018 at 08:17
and selected the winner: "KESK" OOO – (Bidder 2) (Мальцев М.П.) submitting a bid dated of 05.09.2018 11:42
Обоснование: Заявка Участника соответствует требованиям Технического задания.
Notifications have been sent to bidders.
  • On-line Rebidding No.1 is held on 12.09.2018 at 11:00
Price / offerCompany / Date Sorted by descending
The best offer
Hidden
"KESK" OOO
(Bidder 2) Mal'tsev M.P.
05.09.2018 11:42:10
Hidden\"ENERGOSFERA\" OOO
(Bidder 1) Urunchikov R.Iu.
05.09.2018 08:45:39
Total bids: 2