Request for Proposals No. 1455586 
Construction and installation works on modernization of the dust and gas collecting equipment of the filtration and drying department of the main building of the concentrating plant (concrete works on the construction of foundations) equipment;...

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
Item of classifier of goods, works and services:Строительно-монтажные работы (СМР)
Quantity:1 Штука
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:03.03.2020 10:00
Last edited:25.02.2020 05:49
Organizer (Initiator):POLYMETAL TRADING, LTD
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Contract performance security:Согласно условиям ТЗ
Auto-extension
If within the last 10 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 10 minutes from the time the last bid is submitted.
:
10 minutes
Payment terms:According to the terms of the TK
Delivery terms:According to the terms of the TK
Georeferencing:Khabarovsk Territory, Named after Polina Osipenko district
Comments:
LLC "Resources Albazino" invites you to take part in the competition for construction and installation works on modernization of the dust and gas collecting equipment of the filtration and drying department of the main building of the concentrating plant (concrete works on installation of foundations of equipment, work with metal structures, installation of ventilation equipment and ventilation systems, electrical installation works; system automation, commissioning.).

Place of service:
The district named after Polina Osipenko Khabarovsk Krai in the interfluve Amgun - Somnia, on the right bank of the key Oshibochny in its upper reaches. The main building of the concentrating plant. Albazino coordinates (Latitude 52° 51' 17.7" Longitude 137° 53' 2.6").

Terms of work:
1. Start date: 01.06.2020;
2. Completion date: 13.07.2020.

The composition of the works:
1. Contractor shall carry out construction and installation works according to RD and APR No. 683 issued for production of works (Appendix No. 1 to TZ) and carry out commissioning works, previously developed the NDP program.
2. Additional volumes of work may occur in terms of dismantling and restoration of metal service sites. Contractor must specify a% discount on any additional work that is performed in excess of the principal amount specified in the contract (Annex 1 to the base contract, Section I). The Contractor shall be concluded with the Contractor to perform additional volumes of work at the contract prices taking into account% of the fixed discount.

Requirements for the production of CMR:
1. Organization of the production of CMR within the established deadlines with mandatory operational control of the quality of works at the site of work - in accordance with the requirements of the regulatory documentation of the Russian Federation for of the work performed.
2. The Contractor shall provide the Customer with the PRP and the PRP program prior to the commencement of the work.
Construction and installation works will be carried out in the conditions of the existing enterprise, before the start of the work of the PPR and the program of PPR shall be agreed with the Customer's OKS.
3. Contractor employees shall be provided with personal protective equipment, clothing and special footwear.
4. Contractor's engineering units assigned by the Contractor's order shall be instructed by the Customer on the occupational safety and safety, familiarized with the SRS and PB of JSC "Polymetal UK" prior to the commencement of repair work;
5. The Contractor shall comply with the requirements of occupational health and industrial safety, environmental protection, fire safety, regulatory acts and regulations. internal order of LLC "Resources Albazino".
6. When performing repair works, it is obligatory to have a certified engineer of the Contractor who has higher construction education or special construction education and work experience in the specialty not less than 5 years for overall supervision of repair works and Contractor employees.
7. The Contractor shall, during the execution of the works, maintain and after completion, provide the Customer with the execution documentation (general journal of works, certificates of inspection of hidden works, etc.) The current execution documentation shall be provided by the Contractor for review by the Customer at short notice.
8. Contractor's obligation to take all measures to ensure the safety of the property entrusted to it by the Customer and shall be liable for any omission resulting in its loss or damage (Art. 714 of the Civil Code) RF).
9. When performing construction and installation works, be guided by the following rules and regulations: SP 48.13330.2011 - Organization of construction; SNiP 12-03-2001, SNiP 12-04-2002 - Occupational safety in construction. SP 14.13330.2011 Construction in seismic areas and other norms and regulations governing the type of work performed.
10. Ensure the quality of work in accordance with regulatory documents. Contractor's warranty for work performed shall be at least 5 years.
11. Provide geodetic control during the work;
12. Execution documentation is provided by the Contractor in accordance with RD and TR Act on the basis of RD-11-02-2006, SP 48.13330.2011 "Organization of construction". Contractor for the reporting period shall submit to the customer, together with the executive documentation, the certificate of acceptance of the performed works on the form №KS-2 in 3 copies, the certificate of the cost of work on the form №KS-3 in 3 copies, the invoice for payment; provide the Customer with a report on the expenditure of the materials transferred to him.
13. Handling, removal and removal of construction debris shall be carried out by the Contractor.

Minimum requirements for Contractor's machinery and machinery (including the list and quantity for each type of equipment):
1. Concrete mixer, volume 0.25 m3 - 1 unit;
2. Welding machine - 1 unit;
3. Equipment for the organization of lighting of the workplace in accordance with the requirements of the occupational safety;
4. Truck transport for transportation of TMC from the place of storage to the place of work - 1 unit;
5. Manual and auxiliary tools for all types of work (rock drill, drill, screwdriver, tools and accessories for painting works, including scaffolding, ladder, extension cords, etc.) - the number is determined by the composition of the brigade. All employees must be provided with the necessary tools.
* During the work is allowed to use a crane beam of 5 t installed in the workshop of execution of the CMR. Contractor must have a floor control clearance and a slinger certificate (Contractor will be familiarized directly at site of works).

Basic requirements for contractor personnel (quantity/qualification/mode of operation):
1. The number of personnel and the composition of teams shall be formed by the Contractor independently, depending on the type of work performed, taking into account the provision of work in accordance with the Schedule (Appendix No. 3 to the TZ).
2. It is obligatory to have permits on occupational health and safety (certification, certificates, permits), it is obligatory to have permission to work at height.
2.1. Welders shall have NACS Level 1 certification (Technical Unit Group - SC). Contractor's TDI shall have NACS Level 2 certification (Technical Unit Group - SC).
2.2. As part of the installation team of the ventilation system must be a tiner with a discharge not lower than the 3rd, for the manufacture of small units and transitions during the installation of the ventilation system.
The presence of a certified TDI Contractor is required.
The work schedule shall be determined by the Contractor's internal Order, taking into account the requirements of the Customer.

Materials provided by the Customer:
1. The customer provides the TMC, according to the list in Appendix №4 to the TZ.
2. TMC shall be handed over to the contractor at AGOC warehouse on demand.
3. Delivery of the TMC from the place of storage (warehouse) to the place of work is the responsibility of the Contractor. The distance from the warehouse to the OF is 1.2 km.

Accommodation, catering, delivery of personnel to the place of the CMR:
Accommodation and meals on the Customer's site, as well as mobilization of personnel from the gathering place to the Customer's site (and back) shall be carried out at the Contractor's expense. The Customer provides assistance in the organization of meals, accommodation and domestic services, as well as the delivery of Contractor personnel along the route of St. Komsomolsk-on-Amur — section of Albazino and back (watch car). To determine the cost of TK work, the Contractor shall use the information on the relevant tariffs given in Appendix 9 to TK, as well as in the "Proposal Map" file (Appendix 3 to the Letter).
These costs should be included in the cost of the work.

Conditions and terms of mobilization of machines and mechanisms provided by the contractor.
1. Mobilization of equipment (mechanized crew organization) must be carried out before the start of work on the site;
2. Contractor independently and at his own expense provides timely refueling of fuel equipment.
In order to provide the equipment used in the production process with fuel, the Contractor shall enter into a Contract with Polymetal DV LLC (the contractor responsible for the supply and delivery of refueling equipment with fuel at the site of the Albazinsky GOK). The current fuel rates are indicated in the TK.

Requirements to the availability of licensing documentation of the contractor:
In accordance with the requirements of the Urban Planning Code of the Russian F-provision of an extract from the Register of SRO-C members with the admission of work to the GCO is mandatory (the object is GCO). The date of release is not earlier than 01.01.2020.

Health and Safety Requirements:
1. Availability of SRS (occupational safety management system);
2. Availability of the system of health and safety.

This procedure does not constitute a public tender and is not regulated by Articles No. 447-449 of the Part I of the Civil Code of the Russian Federation,
This procedure is also not a public auction and is not subject to Articles 1057-1061, Part II, of the Civil Code of the Russian Federation.
Therefore, this request for quotation procedure is not
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:Харламов Евгений Евгеньевич
Тел.: +7 (42142) 445 05 доб.163

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 03.07.2020 at 05:57
and declared the call for bids void.
Notifications have been sent to bidders.
Total bids: 0