Request for Proposals No. 2651732 
Construction and finishing works at: YANAO g. Novy Urengoy, Gubkin Avenue 14a

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Construction and finishing works at:
YANAO g. Novy Urengoy, Gubkin Avenue 14a
Construction and finishing works at:
YANAO g. Novy Urengoy, Gubkin Avenue 14a

OKPD2 category:
43.22  Работы по монтажу систем водопровода, канализации, отопления и кондиционирования воздуха
43.29  Работы строительно-монтажные прочие
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:06.05.2021 12:00
Last edited:27.04.2021 16:08
Organizer (Initiator):OFS TECHNOLOGIES JSC
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Hide prices and bidders' names during bids submission period:Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Procurement documentation:Not uploaded
Payment terms:4.2. Payment of the cost of Services shall be made by the Customer within 120 calendar days after receiving the invoice of the Contractor, issued on the basis of the Act signed by the Customer
Delivery terms:Novy Urengoy
Georeferencing:Yamalo-Nenets Autonomous District, Novy Urengoy, Magistralnaya str., 14
Comments:
Technical specification

1. General provisions
Subject of work and place of work:
Construction and finishing works at:
YANAO g. Novy Urengoy, Gubkin Avenue 14a, DCF laboratory



1. Requirements set for the time and scope of quality assurance
The quality assurance applies to all structural elements and works performed by the Contractor under the Contract. The guarantee for the performed works is 12 (twelve) months from the date of signing, by the parties of the act of delivery and acceptance of the performed works. In case of detection during the warranty period of operation of nede¬statkov, preventing normal operation of the facility, the Contractor is obliged to eliminate them at his own expense, while the warranty period extended for a period of elimination of shortcomings.
2. Procedure of delivery and acceptance of works.

Acceptance of works is carried out on the basis of the act signed by the parties of the commission acceptance of works (closure of the object) and the act on the acceptance of the performed works, with the application of all documents confirming actual fulfillment.
Completely performed works are subject to acceptance.
In case of non-compliance with the results of the Works to the Technical Task, the parties draw up a bilateral act with a list of necessary improvements. Claims for the completion of the work may be submitted by the Customer within 10 days after the receipt of the act of acceptance of the performed works. The contractor is obliged to make the necessary corrections within 10 days without additional charge.

Requirements of compliance with regulatory documents (licenses, tolerances, permits, approvals):
The contractor (Subcontractor) must be a member of the SRO (in the case of the types of work requiring such membership). In the production of works, the materials used must meet the requirements of quality, safety, sanitary and hygienic standards in the Russian Federation, have certificates compliance, hygienic certificates, if provided by the Law
Repair to perform in compliance with the requirement of SNiP 3.04.01-87 "Insulation and finishing coatings"; MDS 12-30.2006 "Methodical recommendations on the norms, rules and methods of finishing works".
Quality of repair 1. Quality requirements: • Materials with a certificate of compliance with sanitary, fire-fighting standards, standards and specifications applicable on the territory of the Russian Federation must be used for finishing Federation M-bM-^ @M -Finishing work shall be carried out in compliance with the technology of finishing works, according to process maps M-bM-^ @M -The quality of plastering works shall meet the requirements of section MDC 12-30-2006 and section 3 SNiP 3.04.01-87. • The quality of the paint work shall meet the requirements of section 6 of the IBC 12-30.2006 and section 3 SNiP 3.04.01-87. • When painting it is necessary to ensure፦ Compliance with the used materials recommended in the Passport and their quality; - Availability of passports and certificates for all materials used; - storage conditions in accordance with regulatory requirements documents; -observance of technological modes and sequence of application of layers; - monotonicity of coloring, absence of strips, spots, underlines, wrinkles, translucence of the underlying layers; - evenness of the lines painting mating surfaces, painted in different colors; - the correctness of docking grippers when working with filled compounds.

Requirements for the technology of work production: • Completely clean the base of the painting from the old paint; • Remove fragile places and expand the cracks of the plaster; • Restore the plaster close in composition and Strength solution; • Align the base of the painting with a layer of mixture "Vetonit"; • Before painting the plaster, rinse and dry; • On new, repaired, peeled from old layering surfaces, unevenly absorbent, porous, with a showering of sand plaster apply deeply penetrating impregnation until completely absorbed; • Pull the walls with putty; • Walls primed with protective composition from penetration of moisture with a primer • Paint in two times.
Requirements for the organization of work: • Repair and construction works to perform in compliance with the requirements of SNiP 12-04-2002 "Occupational safety in construction". • Before the beginning of repair, perform preparatory work on the organization of the repair area necessary to ensure the safety of repair work, including፦ Fencing;

Names and volumes of work: Construction and finishing works on the installation of internal walls made of drywall, installation of interior doors, window opening, plaster and painting of wall surfaces.


N p/n Name of work unit. Qty

1. Device of walls made of drywall with noise insulation m2 50
2. Installation of interior doors together with the unit Pieces 2
3. The device of a window opening with the installation of a blind window with dimensions of 1.5x2 meters pcs 1

5 Stucco walls and preparation for painting m2 surface 100
6 Wall painting with water-based paint m2 surface 100


Note:
1. When calculating the estimated cost, it is necessary to take into account all related work, according to the technological process of performing a particular work.

2. In the attached scheme of the room white, the existing walls are indicated in white, green highlighted the walls that need to be erected, the yellow color of the doors that need to be installed and red blind window, which also needs to be made and installed.

3. All volumes indicated in the TK are indicative and may change during the work.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Total bids: Hidden