Request for Quotations No. 1027639 
technical specification for performance of works on repair of running gear units tap KZhDJe

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

technical specification for performance of works on repair of running gear units tap KZhDJe
technical specification for performance of works on repair of running gear units tap KZhDJe (Repair)

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:08.06.2018 17:00
Last edited:07.06.2018 13:02
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Alternative bids
Alternative bid is a bid, of which the terms and conditions differ from those established in the bid-related documents.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:50% 50%
Delivery terms:2. The purpose of the repair of:
2.1. Restore health and complete or close to complete running resource re-duktorov crane KZhDJe.

11. The volume of work performed:
11.1. Repair (replacement)-4 x driving crane gearboxes KZhDJe.
12. Terms of execution of works:
12.1. The works are carried out in stages by 2 gearbox
12.2. The work must be performed in accordance with the operating manual cranes railway run KZhDJe-16 and KZhDJe-25»
12.3. At work to provide a guarantee.
13. Materials: Contractor.

14. Payment terms: 50% to 50%

15. StartEnd repairs: the second half of the year 2018.

16. Obligations of a contractor in the field of occupational health and safety:
In the course of work under this contract the Contractor undertakes:
1. To abide by the norms of the current legislation of the Russian Federation, including the law on labour protection, environmental protection Wednesday, industrial and fire safety, other laws and regulations in force in the territory Grew area runners.
2. Prior to execution of the warrant-admission to the works, the contractor shall provide the customer with the following documents:
- a copy of the certificate (SRO) to perform this type of work;
- a copy of the briefing on occupational safety and health training log;
- PORES or BRP or RTI;
- a copy of the certification protocol working on labour protection;
- copies of identity certification ITR on labour protection and the General requirements of industrial safety. When doing work on gas receptacles, working under pressure, using GMP, in electrical installations, conducts fire-bot -copies of certificates for each type of work;
- medical admission personnel;
- copies of certificates, gazojelektrosvarshhikov slingers.
- for copies of the protocols of gazojelektrosvarshhikov for the JWG.
On the implementation of all these conditions, the contractor shall notify the customer in writing with all supporting documents. Failure to comply with the conditions of this item, the Contractor gives the right not to allow the contracting authority to the contractor's execution of works, the delay in execution of works in this case is the fault of the contractor.
3. prior to the registration of attire-the admission of all employees of the contractor are obliged to undergo induction training of customer's specialists have (you have a document confirming identity and age). By manufacture of works on along-the admission of all the employees of the contractor must have certified clothing, footwear and other personal protection equipment necessary to perform this type of work.
Failure to comply with the conditions of this item, the Contractor gives the right to the customer not to allow the contractor to perform work, failure to perform work in such cases, tea is the fault of the contractor.
4. Comply with the requirements of internal normative documents of the customer (with whom the contractor is made aware of this until the signing of the additional agreement), namely:
- instructions on occupational safety and health and fire safety instructions;
- provisions on the use of orders-tolerances in the production of works of increased danger at EPM-NJeZ ".
5. If the fault of the contractor for fires, accidents, incidents and accidents-teas with employees of OJSC "EPM-NJeZ" that occurred during the execution of the work, the Contractor undertakes to indemnify the damages caused to the customer, and other expenses incurred.
6. the customer shall not be liable for injury, injury or death of any employee of the contractor, in case of violation of the requirements of occupational safety regulations, industrial and fire safety, industrial health and safety measures works.
7. the customer shall have the right at any time to monitor the Contractor, the provisions of this section. In the event of a breach by the contractor (subcontractor), industrial and fire safety, occupational safety, and other requirements for the safe execution of works, the customer shall be entitled to charge the Contractor for each case of violation fine of 20 000 rubles. Each case of violations issued an act of arbitrary form in two copies. The Act is signed by the representatives of the contractor and the customer. In case of failure of the contractor from the signing of the Act, it shall be prepared by the employer unilaterally, indicating that the contractor abandoned the signature. One instance of an act in three days with a covering letter is sent to the contractor, the second shall be retained by the customer. Payment of a fine shall be made on the invoice within 5 days of receipt, either by withholding money from the amount payable to the contractor for work performed. The total amount of the fine may not exceed 50% of the contract value, shall be accepted by the parties economically reasonable, is not excessive and is not subject to reduction. 333 CIVIL CODE.
8. The contractor shall be obliged to collect and remove beyond the Enterprise Customer all debris and waste resulting from the execution of the works. By agreement of the parties which is decorated in writing, it is possible to transfer the waste to the customer.
9. Use and bringing into the territory of the customer substances of alcoholic or drug intoxication, or psychotropic or other inebriating substances shall be prohibited. The customer does not allow on its territory an employee or contractor (subcontractor) is intoxicated, and when it detects an employee or contractor (subcontractor) on its territory, with signs of inebriation, immediately removes the last beyond notifies about the contractor's supervisor or other authorized person, and also have the right to withdraw such employee badge. Person, once "captured" under the influence of alcohol or drugs in the future on the territory of the customer are not permitted.
The contractor shall be liable to a fine of 20 000 (twenty thousand) rubles for each case finding on the customer's site (as well as the attempt to pass) the contractor personnel (subcontractor) is in condition of alcohol, narcotic or other intoxication. Appropriate proof of intoxication is the Act of medical examinations, and upon cancellation of an employee (engaged to perform work of a person) from survey-Act of renunciation of the medical examination and the fact that persons act intoxicated with indication of external signs of intoxication (alcohol breath odor, the coordination of movements, fingers shaking (tremor), irritability, aggressiveness, lack of concentration, inadequate reactions I'm on the words and actions, incoherent speech, narrow pupils, paleness or redness of the skin, etc.). These documents shall be drawn up with the participation of representatives of the private security company OOO "ChOO graphite-Novocherkassk.
Liability under this paragraph shall be due in the case of fait accompli consumption causing intoxication substances, which is defined by the presence of absolute ethyl alcohol in a concentration exceeding the possible amounts arnuju measurement, namely 0.16 milligrams per one liter of exhaled air, or in the case of narcotic drugs or psychotropic substances in the human body.
Payment of a fine shall be made on the invoice within 5 days of receipt, either by withholding money from the amount payable to the contractor for work performed. The total amount of the fine may not exceed 50% of the contract value, shall be accepted by the parties economically reasonable, is not excessive and is not subject to reduction. 333 CIVIL CODE.
10. Failure to comply with the requirements of this section by the contractor is a significant breach of the terms and conditions of the contract and placing entitles the customer to cancel the present agreement unilaterally without any obligations the customer for damages Contractor, associated with such termination.
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
Party, participating in the procedure (who offer) before the expiry of the deadline, is required to download to your system the following documents:
1. Bylaws (as amended and supplemented, if they were).
2. Certificate about State registration.
3. Certificate of tax registration.
4. Extract from the UNIFIED STATE REGISTER.
5. Balance sheet as of the last reporting date with tax authority stamp of acceptance.
6. Documents confirming the powers of the representative to sign the documents:
-Decision (Protocol).
-Power of attorney.
7. Proposal for execution of works (see file "work Proposal")
8. Contact person: Aleksandr Aleksandrovich topilin, head of the Transportation Department, phone 8 (8635) 29-44-96, fax 8 (8635) 29-49-69, e-mail: Atopilin@energoprom.ru
9. Certificate of conformity to requirements of standard ISO 9001: 2008 (if available)
This request is not a notice about the contest or an auction and does not confer any rights of parties entails no duties except directly specified in the notification.
10. Executive requirements:
-Permits (CPO, licenses, tolerances).
— Development of PPR, Executive LEAD, RTI.
— Availability of certification Manager, ENGINEERS, working on industrial safety to GCO.
— The availability of medical staff work at the tolerance of GCO.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 25.06.2018 at 12:51
and selected the winner: LRS OOO – (Bidder 1) (Коваленко А.Е.) submitting a bid dated of 06.06.2018 14:54 totalling to 210 813,56 RUB (price excl. of VAT)
Notifications have been sent to bidders.
Total bids: 2. More >>