Request for Proposals No. 1459148 
CGE Section №10 Restoring the serviceability of the building inv. No. 1120 according to the results of the conclusion No. 116-04-ЗС / 19 EXPERTISE OF INDUSTRIAL SAFETY.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:12.03.2020 17:38 (was extended by 38 min, 22 sec)
Last edited:27.02.2020 16:16
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:In a commercial offer
Delivery terms:1. Application of EPM-NEZ JSC, Novocherkassk
2. The purpose of the work.
2.1. Restoring the operational suitability of the building of the central heating station section 10 in the axes Р-Я 8-39 according to the results of the conclusion No. 116-04-ЗС / 19 EXPERTISE OF INDUSTRIAL SAFETY.
3. The list and scope of work performed.
3.1. The building of block No. 4 of the TsGE section 10 in the axes of R-Ya 8-39. look in TK
Note: The costs of installation, dismantling of temporary sites, installation, removal of winches, rigging, devices for lifting material, the contractor must consider in accordance with the developed PPR. These volumes are not included in the list of volumes of work by the customer.
4. Mechanisms, equipment and tools provided by the Contractor.
4.1. Work is performed from customer’s material
4.2. Lifting mechanisms and mechanisms for loading and installation works are provided by the contractor.
4.3. Electric welding and gas cutting equipment, power tools, oxygen, propane, auxiliary materials are provided by the contractor.
5. Requirements for the Contractor.
5.1. The contractor must have the necessary production and human resources to carry out this work, be a member of a self-regulatory organization (SRO).
5.2. To clarify the conditions for the performance of work, familiarization with the object, it is desirable that the representatives of the Contractor arrive at the Customer.
5.3. The contractor in his proposal indicates the payment procedure and other conditions.
5.4. Certification of the head, engineering and industrial safety and labor protection performers at the public educational institution. According to Appendix No. 1.
5.5. Ensuring HSE measures with safe methods for performing work at the facility.
5.6. The Contractor is obliged to provide copies of documents confirming the availability of labor protection services and / or labor protection specialists in the contractor (order of appointment to the contractor, certificate of labor protection specialists) or an agreement with an accredited organization in the field of services labor protection.
5.7. The contractor before the start of work provides a schedule of work.
5.8. The contractor carries out visually measuring control of welded joints with the registration of the protocol.
5.8.1. The contractor monitors the volume of exported construction waste and scrap metal by weight.
5.9. The contractor provides a local estimate.
6. Terms of work
6.1. Work at the existing enterprise in the technological windows provided, depending on the equipment load.
6.2. Development of PPR or PPRK carried out by the Contractor.
6.3. Lifting mechanisms, rigging devices in accordance with PPR for installation are provided by the Contractor.
6.4. Vehicles for transportation of materials to the facility from warehouses, as well as scrap metal are provided by the Contractor
6.5. The object is a single-span one-story industrial building.
7. Turnaround time.
7.1. Start of work - April 2020
7.2. Completion of work - October 2020
8. A list of documents required for the execution of orders - tolerances at the enterprise is attached to the terms of reference. Annex 1
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
The participant who participated in the procedure (made a proposal), before the deadline for accepting applications, is obligated to upload the following documents to the system:
1. Articles of Association (with all the amendments, if any).
2. Certificate of the state registration.
3. Certificate of tax registration.
4. Extract from USRLE.
5. Balance sheet as of the last reporting date with tax authority stamp of acceptance.
6. Documents confirming the powers of the person authorized to sign the documents:
— Decision (Protocol).
— Power of attorney.
7. Proposal for work (see file "Proposal for work")
8. Contact person: Tetslav Vladimir Edvinovich - Head
OEiNZiS, phone 8 86 532-9-42-13, fax 8 86352 9-46-18
E-mail: VTetslov@energoprom.ru
9. Certificate of conformity to requirements of ISO 9001: 2008 (if available)
This request does not constitute a notification of tender or auction and shall not grant any rights to the participants and shall not entail any obligations except those explicitly stated in the announcement.
10. Requirements for the Contractor:
- Permitting documents (SRO, licenses, admissions).
- Development by the executor of PPR, PPRK, RTI.
- Availability of certification of the head, engineers, industrial safety workers at the public educational institution.
- The presence of medical admission of personnel to work at the public educational institution
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 19.03.2020 at 14:32
and declared the call for bids void.
Notifications have been sent to bidders.
Total bids: 4. More >>