TSC. Pump-accumulator station TPC-1. Visualization system of technological parameters "
1. Construction-Assembly works, 2. developing estimates for the NDP
3. Starting-up and adjustment works
Construction and installation work in accordance...
TSC. Pump-accumulator station TPC-1. Visualization system of technological parameters "
1. Construction-Assembly works, 2. developing estimates for the NDP
3. Starting-up and adjustment works
Construction and installation work in accordance with estimates no. 43079; 43079-1
Commissioning-developing estimates Podpjadchikom
1. Delivery of the equipment, specified in customer's delivery estimates
2. Materials-delivery Contractor construction, installation and commissioning (Turnkey)Collapse
Not applicable. Proposal shall cover the entire lot.
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Ranking of bids
In the course of bidding, a price-based rank (position) shall be assigned to a quotation.
Assignment of the 1st rank (position) to a bid does not imply the bidder's winning, but enhances the bid's preferability for the Buyer when selecting the winner, all other factors being equal.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
In calls for bids with bids ranking, bid submission deadline will automatically be extended in the same manner if the rank of a bidder changes.
:
30 minutes
Payment terms:
*
Delivery terms:
June-August 2018g.
Georeferencing:
Chelyabinsk region, Chelyabinsk, Lenin district
Comments: provider qualification requirements:
1. Experience of realization of similar projects (the reviewer worksheet, reviews)
2. Certificate of admission to certain kinds of work (SRO)
3. The presence of documents certifying the qualification of responsible persons for safe production of works for labour safety, industrial and fire safety, electrical safety into categories a, b, g.
4. Our own logistical framework required to perform these works
The order of delivery and acceptance of the results of the procedure and reporting forms, the Executive Director of services to the customer:
1. Surrender-acceptance of work is performed in accordance with requirements of snip 3.01.04-87 "Acceptance into operation of completed construction projects. «General provisions». 2. Acceptance of works is performed in the following: porjadjake. The contractor no later than 25 the number reporting month provides for consideration to the customer for verification and signing acceptance certificate of executed works (form # KS-2), not later than 3 (three) working days prior to the end of the reporting month cost of certificate works and costs (form # KS-3) and the invoice established by the RUSSIAN FEDERATION sample. 3. The contractor is obliged to transfer to the customer Executive documentation, designed in accordance with the requirements of RD-11-02-2006. 4. Upon completion of the acceptance of the entire scope of work, the parties sign acceptance of the finished construction of the object (form # KS-14).
Services Procurement Manager
Victoria Alexandrovna Kuzmina
+ 7 351 259 03 61
Viktoriya.Kuzmina@chelpipe.ru
Curator on technical matters Ushakov Sergey Vladimirovich
Leading engineer of electrical installations and equipment
255-75-57
Sergey.Ushakov@chelpipe.ru
Registration and enrollment of participants on the site free-Center B2b, electronic signatures are not required. When questions about registration and hosting of applications accessed by Tel. 8 (495) 989-85-19 Ext. 7610; 8 (800) 555-85-19 Ext. 7610.
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.