Per-item bid submission: | Not applicable. Proposal shall cover the entire lot. |
Restriction on submission of a bid higher than previously submitted Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased. : | Yes |
Alternative bids Alternative bid is a bid, of which the terms and conditions differ from those established in the bid-related documents. : | Yes |
Upload of bid-related documents required Bids not supported with documentation will not be considered. : | Yes |
Ranking of bids In the course of bidding, a price-based rank (position) shall be assigned to a quotation.
Assignment of the 1st rank (position) to a bid does not imply the bidder's winning, but enhances the bid's preferability for the Buyer when selecting the winner, all other factors being equal. : | Yes |
Auto-extension If within the last 5 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 5 minutes from the time the last bid is submitted.
In calls for bids with bids ranking, bid submission deadline will automatically be extended in the same manner if the rank of a bidder changes. : | 5 minutes |
Payment terms: | The contractor independently issues a permit for the production of excavation and construction works, bears full responsibility in case of violation of the work.
Opening of an excavation warrant.
Permits for construction and installation works, cutting down trees, work in the security zone of power lines, etc. The contractor receives it independently.
To develop and coordinate, in accordance with the established procedure, the traffic management scheme (ODD), including its coordination with the Customer and Sibsteklo LLC.
Construction and installation works should be organized and carried out in accordance with the work production project developed by the Contractor, taking into account all the requirements imposed on them. Before starting work, coordinate the PPR with the Customer and Sibsteklo LLC.
Provide the Customer with a detailed schedule of work with an indication of the actual deadlines for all stages of work.
The Contractor pays for the necessary tolerances and approvals at its own expense. |
Delivery terms: | To complete the works with all the materials necessary for the performance of construction and installation works, in strict accordance with the technological sequence of construction and installation works, within the time limits established by the calendar plan and schedule of work.
In the process of performing the work, organize timely visits to the facility and acceptance of completed works by the Customer's representatives in accordance with the Order on the appointment of responsible persons (geodetic works, SMR, survey of hidden works and fixing volumes) with mandatory entry of appropriate entries in the General Work Log (form KS-6).
Upon completion of the work stages, timely transfer the executive documentation for consideration and signing to the Customer's representatives. The contractor draws up the executive documentation throughout the entire period of production of the CMP in accordance with the SNiP and transfers it to the Customer in full upon completion of the construction of the facility.
At all stages of the work, geodetic support of construction should be carried out with the phased compilation of geodetic executive schemes and acts and their timely submission for consideration and approval to the Customer.
To transfer the dismantled equipment to the Customer.
All work must be performed in accordance with the regulatory and technical documentation (NTD): SNiP, PUE; guidance documents; industry standards, etc. documents.
All changes in design decisions must be agreed with the Customer and the project organization before the start of work.
Fulfillment of all technical specifications issued by interested enterprises and organizations in accordance with design decisions.
The Contractor receives all necessary approvals from third-party organizations arising in the course of work, as well as obtaining an Act of admission to the Rostechnadzor SZ independently. |
Georeferencing: | 630047, Russia, Novosibirsk region, Novosibirsk, Dargomyzhsky str., 8A |
Comments: 1. Proposals from Bidders are accepted, according to the attached Requirements Specification.
2. This request for proposals is not a competitive bidding process or a public tender within the meaning of Articles 447-449, 1057-1061 of the Civil Code of the Russian Federation. All actions prior to the signing of the contract with the winner of the competition are considered pre-contractual work and do not impose obligations on the organizer exceeding those listed in the terms of the competition.
3.All offers are accepted through the E-Marketplace |
Venue of bidding: | This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document. |
ВАЖНО:: | Данный запрос предложений не является торгами или публичным конкурсом в понимании ст. 447-449, 1057-1061 ГК РФ. Все действия до момента подписания договора с победителем конкурса считаются преддоговорной работой и не накладывают на организатора обязательств, превышающих перечисленные в условиях конкурса.
Все вопросы по ТП размещать во вкладке "разъяснения". |
По вопросам участия на ЭТП звонить по телефону:: | 495-532-85-19, доб. 7610, 7620 |
Все вопросы по торговой процедуре: | Через вкладку "Разъяснения" |
По техническим вопросам: | Михаил Иванович
+7-913-794-79-55 |