Request for Proposals No. 2486310 
Repair work of the PTVM 30m boiler No. 7 (serial number 2946) installed in the central boiler room EPM-NEZ JSC.

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available

Repair work of the PTVM 30m boiler No. 7
(serial number 2946) installed in the central boiler room
EPM-NEZ JSC.
See terms of reference (Complex service)

OKPD2 category:
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:11.11.2020 20:50 (was extended by 3 h, 50 min, 48 sec)
Last edited:27.10.2020 11:01
Organizer (Initiator):El 6 Novocherkassk
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Restriction on submission of a bid higher than previously submitted
Bidding initiator has set a restriction on submission of a bid with a price which is higher than the price of the previous bid submitted by the bidder. Once the bid is submitted, the stated price can not be increased.
:
Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:Upon rendering of works
Delivery terms:1. Application of JSC "EPM-NEZ", Novocherkassk
2. Objective
2.1. Recovery of the boiler unit.

3. Content of work
3.1. The scope of work on the repair of the PTVM 30m boiler includes:
3.1.2. Dismantling, installation of all heating surfaces and boiler collectors.
3.1.3. Dismantling, installation of lining, thermal insulation of the boiler in the amount necessary to perform work on replacing the pipe part of the boiler (p. 3.1.2.)
3.1.4. Expertise of industrial safety at the end of work.
3.1.5. Commissioning works at the end of the work.
Boiler tube requirements:
- pipe: DN 28 mm, wall 3.0 mm, seamless cold-worked steel pipe, steel - St20, according to GOST 8733-74;
- pipe: DN 83 mm, wall 3.5 mm, seamless hot-deformed steel pipe, steel - St20, according to GOST 8731-74.
- pipe: DN 60 mm, wall 3.0 mm, seamless hot-deformed steel pipe, steel - St20, according to GOST 8731-74.

4. Terms of work

4.1. Commencement of work - November - December 2020.
4.2. Completion of work - March-August 2021. (start of dismantling March 2021)


5. Requirements for the Contractor

5.1 The contractor must have the necessary production and human resources to carry out this work, be a member of a self-regulatory organization (SRO).
5.2 To clarify the terms and conditions of the work, familiarization with the object, the arrival of the Contractor's representatives to the Customer is mandatory.
5.3 The Contractor in his commercial offer indicates the procedure for payment for work and other conditions.
5.4 Attestation of the manager, engineers and technicians and executors for industrial safety and labor protection at HIFs in accordance with Appendix No. 1.
5.5 Ensuring health and safety measures, safe methods of work at the facility.
5.6 Before starting work, the Contractor is obliged to develop technological documentation.
5.7 Before issuing a work permit for work, the Contractor is obliged to provide the Customer with the following documents: copies of documents confirming the presence of a labor protection service and / or a labor protection specialist in the contractor (order for appointment to a position in the contractor, certificate of a labor protection specialist) or the existence of an agreement with an accredited organization in the field of labor protection services.
5.8 After the completion of the work, the contractor hands over to the customer the as-built documentation in accordance with RD-11-02-2006 dated 26.12.06. and other regulatory documents.
5.9 Provision of warranty obligations for at least 24 months.
5.10 Employees involved in the performance of work must have professional training corresponding to the nature of the work performed with a mark in a special certificate of training and passing exams in certification commissions, know and comply with the requirements of technological documents and instructions for carrying out the declared work.

6. Work safety

When performing work, the contractor must comply with the requirements of the following rules:
- labor protection rules during the operation of electrical installations;
- rules for the technical operation of electrical installations of consumers;
- safety rules for hazardous production facilities where lifting structures are used;
- electrical installation rules;
- fire safety rules;
- rules for labor protection when working at height POT RM-012-200;
- rules of environmental, sanitary and hygienic and other norms in force on the territory of the Russian Federation and to ensure safe working conditions for the life and health of people.
For the performance of work, the contractor must undergo an introductory briefing. All work performed on the territory of EPM-NEZ JSC must be carried out in accordance with the regulation "On the use of permit work orders in the performance of high-risk work at EPM-NEZ JSC.
Georeferencing:346413, Russia, Rostov region, Novocherkassk, Aluminum platform
Comments:
Participant who has submitted a bid before bids submission deadline shall upload the following documents:
1. Articles of Association (with all the amendments, if any).
2. Certificate of the state registration.
3. Certificate of tax registration.
4. Extract from USRLE.
5. Balance sheet as of the last reporting date with tax authority stamp of acceptance.
6. Documents confirming the powers of the person authorized to sign the documents:
— Decision (Protocol).
— Power of attorney.
7. Work proposal (see the file "Work proposal")
8. Contact person: Lymar Alexander Fedorovich, tel. 8-8635-29-47-73, email address: Alimar@energoprom.ru
9. Certificate of Compliance with ISO 9001: 2008 (if applicable)
This request does not constitute a notification of tender or auction and shall not grant any rights to the participants and shall not entail any obligations except those explicitly stated in the announcement.
10. Requirements for the performer:
- Permitting documents (SRO, licenses, permits).
- Development by the contractor of PPR, PPRK, RTI.
- Availability of attestation of the head, engineering technician, industrial safety workers at HIF.
- Availability of medical clearance of personnel to work at HIF.
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Контактное лицо:
E-signature info:Signed with e-signature

This call for bids is archived
Participation in bidding is no longer possible. You may wish to check similar calls for bids currently available
  Submit a question
Latest submitted bids
Status of bidding: archived.
Organizer's decision:
The Organizer has announced the results on 18.01.2021 at 08:53
and selected the winner: OOO "YUGDONENERGO" – (Bidder 2) (Климушин Г.Н.) submitting a bid dated of 11.11.2020 20:09 totalling to 10 420 000,00 RUB (VAT free)
Notifications have been sent to bidders.
Total bids: 5. More >>