Request for prices based on the results of the open competition № 53210 on the right to conclude a contract for the execution of exploration work, the development of working documents and the construction and installation works Lot № 5: -The...
Request for prices based on the results of the open competition № 53210 on the right to conclude a contract for the execution of exploration work, the development of working documents and the construction and installation works Lot № 5: -The object of Bagtionovsky district, according to annex № 5.26 Execution of survey works, development of working documentation and execution of construction and installation works Lot № 5: -The object of Bagtionovsky district, according to annex № 5.26Collapse
Not applicable. Proposal shall cover the entire lot.
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Minimum bid increment/decrement
The Organizer has established a minimum decrement for a Bidder's changing the total lot price from their previously submitted proposal.
:
0,6% of total amount
Supplier should not be recorded in the register of mala fide suppliers
The Organizer has set a requirement as to the supplier's not being recorded in the register of mala fide suppliers. Supplier's compliance with this requirement shall be checked by the Organizer on their own.
:
Yes
Participation of small and medium businesses
Organizer has initiated the bidding only for small and medium businesses to participate. Verification of compliance with the criteria for being qualified as small and medium businesses is to be performed by the organizer.
:
Участниками данной закупки могут быть только субъекты малого и среднего предпринимательства
Auto-extension
If within the last 30 minutes of bid submission period a new bid is submitted, then bid submission deadline will automatically be extended by 30 minutes from the time the last bid is submitted.
:
30 minutes
Payment terms:
payment of the cost of the executed works is made by the customer in the following order:
Payment of the work performed on the survey work, development of working documentation (1 stage) on the object is carried out on the basis of the act of acceptance of completed design works and invoices within 15 calendar days from the date of signing Specified documents.
- If there is a positive conclusion about the verification of the estimate of the estimated cost of the object at the time of delivery-acceptance of the survey works and work on the development of working documents (1 stage) for each object, payment is made on Based on the certificates of delivery and acceptance of executed works and invoices, within 15 calendar days from the moment of signing of the mentioned documents.
- In the absence of a positive conclusion on the validation of the estimate of the estimated cost of the object at the time of delivery-acceptance of the survey works and work on the development of working documents (1 stage) for each object payment is made in Following order:
85% of the cost of exploration works and work on the development of working documents shall be paid on the basis of the acts of delivery and acceptance of the executed works and invoices, within 15 calendar days from the date of signing of these documents.
The final calculation is carried out on the basis of the corrected in accordance with the positive conclusion on the validation of the estimate of the estimated value of the object of the acts of delivery and acceptance of the executed works and invoices, within 15 Calendar days from the moment of signing of the mentioned documents.
- If there is a positive conclusion about the verification of the estimate of the estimated cost of the object at the time of delivery-acceptance of the completed construction and installation works with equipment delivery (2 stage) for each object payment is made on the basis Acts of acceptance of executed works (Form № KS-2), certificates on cost of executed works and expenses (Form № KS-3), acts of results of works and invoices, within 15 calendar days from the moment of signing of the mentioned documents.
- In the absence of a positive conclusion on the validation of the estimate of the estimated cost of the object at the time of delivery-acceptance of construction and installation works with equipment delivery (2 stage) for each object payment is made in Following order:
85% of the cost of construction and installation works with the supply of equipment is paid on the basis of certificates of acceptance of completed works (Form № KS-2), references on the cost of work performed and costs (Form № KS-3), acts of work results and invoices, within 15 (fifteen) calendar days from the moment of signing of these documents.
The final calculation is carried out on the basis of the corrected in accordance with the positive conclusion on the validation of the estimate of the estimated value of the object of certificates of acceptance of executed works (Form № KS-2), references on the cost of executed Works and expenses (Form № KS-3), acts of results of works and invoices, within 15 (fifteen) calendar days from the moment of signing of the mentioned documents.
Calculations are made by transferring non-cash funds to the bank details of the contractor.
Delivery terms:
The period of work execution: Term of carrying out of prospecting works, development of working documentation and execution of construction and installation works – no more than 45 days from the moment of signing the contract:
Carrying out of prospecting works and development of working documentation – 15 days;
Execution of construction and installation works – 30 days.
Venue of bids examination:
г. Калининград, ул. Театральная 34
Date and time of bids consideration:
16.11.2018 18:30
Results date and time:
19.11.2018 18:30
Georeferencing:
Россия, Калининградская область,
Comments: the price request organizer, according to the decision of the Purchasing Commission, has the right to refuse the request of prices before the date and time of the deadline for submission of bids for participation in competitive purchase. The decision to cancel the competitive purchase is placed in the unified information system on the day of making this decision. All participants of the price request, having registered their participation in the price request through the ETP, will receive corresponding notices in the order established by the rules of this system.
Venue of bidding:
This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.
Procurement documents provision procedure:
Procurement documents in electronic form are available free of charge at B2B-Center marketplace (www.b2b-center.ru) starting from the date of publication of the procurement procedure.
The Organizer has announced the results on 19.11.2018 at 15:33
and selected the winner: "Energiia" OOO – (Bidder 1) (Шуршилин С.С.) submitting a bid dated of 02.11.2018 14:47 totalling to 646 610,17 RUB (price excl. of VAT)
Обоснование: Победитель выбран по наименьшей цене предложения.
Notifications have been sent to bidders.
On-line Rebidding No.1 is held on 19.11.2018 at 12:00