Request for Proposals No. 4290738 
Selection of a contractor to perform 2 stages of construction and installation work at the facility within the framework of the project: Construction of the building of the chemical and analytical laboratory of LLC "GRK "Bystrinskoye"

Selection of a contractor to perform 2 stages of construction and installation work at the facility within the framework of the project: Construction of the building of the chemical and analytical laboratory of LLC "GRK "Bystrinskoye"

Tag:Здания и сооружения (строительство)
Quantity:1 шт.
Total price:Price not specified
Currency:RUB
Contract award criteria:price excl. of VAT (show both prices)
Publication date:
Bid submission deadline:23.01.2026 10:00
Плановая дата подведения итогов
Организатор указал предполагаемую дату подведения итогов. Если в процедуре не будут подведены итоги при наступлении этой даты, то участники могут запросить их самостоятельно
:
23.01.2026
Last edited:14.01.2026 06:38
Organizer (Initiator):"GRK "BYSTRINSKOE" OOO
Additional info
Per-item bid submission:Not applicable. Proposal shall cover the entire lot.
Hide prices and bidders' names during bids submission period:Yes
Upload of bid-related documents required
Bids not supported with documentation will not be considered.
:
Yes
Possibility of bid submission in a different currency
When applying, bidders can choose a currency different from the one stated for the procedure. For the purposes of bids evaluation, the prices provided in other currencies will be converted based on the official currency rate of the Russian Central Bank as of the date of publication of a call for bids.
:
Yes
Payment terms:Option 1. Payment in advance using a commercial loan

The advance payment in the amount of 20% of the cost of the work is paid on the first working Thursday after the expiration of 15 working days from the date of receipt by the Customer of the invoice for the advance payment and subject to the provision by the Supplier of an independent guarantee for the amount of the advance, which has a validity period that expires not earlier than the deadline for the fulfillment of obligations, plus 45 (forty-five) working days. The guarantor Bank is coordinated with the Customer.
Payment for the work performed shall be made minus the amount of the credited advance payment on the basis of the primary accounting document signed by the Parties within 360 (three hundred and sixty) calendar days from the date of acceptance of the work.
The deferral of payment is granted on the terms of a commercial loan, which provides for the payment by the Customer to the Supplier of interest for the use of a commercial loan in accordance with the procedure and on the terms of the contract.
Interest for the use of a commercial loan is accrued on the amount of the monetary obligation for the work undertaken, starting from the 15th day of deferral of payment (inclusive) in the amount of the key rate of the Bank of Russia (in% per annum), effective for each calendar day of the interest calculation period for the use of a commercial loan, increased by X% (the amount of the increase is agreed by the parties on the date of signing contract), for the amount of actual debt (minus security payments), based on the actual number of days of use of a commercial loan.
Payment of interest for the use of a commercial loan is made after the provision of the originals of the primary accounting documents on a monthly basis based on the interest calculation received from the Supplier, drawn up in the form for the past month.
The Supplier has the right to transfer its rights under the contract to third parties with the prior written consent of the Customer. Written consent, including the signing of a Notification of factoring in the form agreed by the parties.

Option 2. Payment without an advance using a commercial loan

Advance payment is not provided.
Payment for the work performed shall be made on the basis of the primary accounting document signed by the Parties within 360 (three hundred and sixty) calendar days from the date of acceptance of the work.
The deferral of payment is granted on the terms of a commercial loan, which provides for the payment by the Customer to the Supplier of interest for the use of a commercial loan in accordance with the procedure and on the terms of the contract.
Interest for the use of a commercial loan is accrued on the amount of the monetary obligation for the work undertaken, starting from the 15th day of deferral of payment (inclusive) in the amount of the key rate of the Bank of Russia (in% per annum), effective for each calendar day of the interest calculation period for the use of a commercial loan, increased by X% (the amount of the increase is agreed by the parties on the date of signing contract), for the amount of actual debt (minus security payments), based on the actual number of days of use of a commercial loan.
Payment of interest for the use of a commercial loan is made after the provision of the originals of the primary accounting documents on a monthly basis based on the interest calculation received from the Supplier, drawn up in the form for the past month.
The Supplier has the right to transfer its rights under the contract to third parties with the prior written consent of the Customer. Written consent, including the signing of a Notification of factoring in the form agreed by the parties.

The terms of the commercial loan are contained in Appendix No. 7 to this Invitation.
Delivery terms:In accordance with the Requirements Specification
Georeferencing:Zabaykalsky Krai, Gazimuro-Zavodsky district
Venue of bidding:This call for bids is held in electronic form on the e-marketplace of B2B-Center group (www.b2b-center.ru). Bids shall be submitted in the form of e-document.

 
Terms of participation
To view the terms of participation, please get registered
Submit a question
Latest submitted bids
Status of bidding: active.
Total bids: Hidden